Business hotel 2150㎡ printed slate (Yunlong) wall construction case

The business hotel project is located in Ziyang City, Sichuan Province, and the main wall material is printed slate flexible stone (Yunlong), used for hotel corridors, elevator lobbies, guest rooms and dry areas of washrooms. The construction area is about 2150 ㎡ (including public areas), completed by 6 people in 34 working days.

Published time:

Introduction

The business hotel project is located in Ziyang City, Sichuan Province, and the main wall material is Printed board rock Flexible Stone (Yunlong), used for hotel corridors, elevator lobbies, guest rooms and dry areas of restrooms, with a construction area of approximately 2150 ㎡ (including public areas), completed by 6 people in 34 working days. This article explains the material selection basis, quantity and schedule estimation, construction control points, application images and common questions at once.

  • Project: Business hotel · Hotel corridors, elevator lobbies, guest rooms, and dry areas of restrooms
  • Location: Ziyang City, Sichuan Province
  • Main material: Printed slate flexible stone (Yunlong)
  • Construction area: approx. 2150 ㎡
  • Schedule: 34 working days / 6 people
  • Implementation standards: JG/T 540-2017

Project file

Project Content
Project nameHotel corridor wall material—Printed slate (Yunlong) flexible stone application case (Ziyang)
Space typeHotel corridor
Business typeBusiness hotel
CityZiyang City, Sichuan Province
Scale96 guest rooms + corridors on 5 floors
Construction locationHotel corridors, elevator lobbies, guest rooms and dry areas of restrooms
Main material.Printed Slate Flexible Stone (Yunlong)
Construction areaApprox. 2,150 ㎡ (including common areas)
Construction period34 working days
Number of construction workers6 people
Implementation standardsJG/T 540-2017"Flexible Stone-like Facing Materials for Buildings"

1. Customer industry usage scenario: the real wall requirements of a business hotel

  1. Corridors are spaces viewed repeatedly, with the lowest tolerance for error. A guest may walk through the guest room corridor four times a day; staying three days means twelve times. Any seam misalignment or concentrated color difference will be seen repeatedly. The importance of layout and batch management in spaces like corridors is higher than in other areas.
  2. Light strip wall washing magnifies all flaws. Corridors usually use skirting lines or ceiling-concealed light strips to wash light onto the walls. Light travels close to the wall surface, revealing substrate undulation, joint misalignment and panel waviness. This is why substrate flatness requirements are higher in hotel projects than in restaurant projects.
  3. The direction of the metal edge trim strip must align with the grain direction. Hotel corridors often use dark metal edge trim strips to press the seams. If the direction of the edge trim strips crosses the bedding direction of the slate, the facade will look messy; a parallel approach gives clean lines and is also easier to pass acceptance.
  4. Materials for five floors must be from the same batch. If different floors of the same building receive materials in separate batches, color differences will be exposed at locations such as stairwells and elevator lobbies where "two batches of material meet." The approach is to order enough at once, or at least lock in the same batch, and mix the material before installation.
  5. Moisture-proofing and underground spaces. Hotels often have basements and semi-basement corridors with higher humidity than above ground. Materials that do not absorb water and resist mold are basic requirements; individual water seepage areas still require waterproofing treatment first, and materials cannot replace the waterproofing layer.
  6. Accessibility for fire protection and maintenance. Corridor walls often have fire hydrant cabinets, access panels, and evacuation signs. Layout must avoid these devices and ensure cabinet doors can open fully; making non-openable equipment cabinets into "removable panels" is a common practice.

II. Material comparison: why choose "printed slate flexible stone"

When comparing wall materials side by side, what really determines the selection is often not "which one looks better," but rather whether the base layer can bear the load, whether the schedule can be compressed, and whether the shape can be achieved.

Comparison item Printed Slate Flexible Stone Tile / Slab. Natural stone. Traditional wood veneer
Weight per square meterApprox. 3.5–3.9 kg/㎡Noticeably heavier, substrate reinforcement requiredHeaviest; mostly requires dry hangingIncludes thicker base coat
thickness2.3–2.8 mm6–12 mm15–30 mmIncludes base coat 15 mm or more
Curved surface and columnCan be curved within a certain radius, covering the entire surfaceSmall pieces must be cut and pieced together, with dense jointsRequires waterjet processing; cost and lead time increaseRequires steam heat bending or slitting
Construction methodNo skeleton required, full adhesion after leveling the baseSpecial adhesive, high requirements for joint-gap processMostly dry-hung, requires embedded partsRequires furring strips or a backing board
Moisture-proof and mold-proofDoes not absorb water, does not swellIt does not absorb water itself, but dirt easily collects in the seamsSome stone absorbs waterProne to swelling and mold when damp
ScheduleShort, no wet work or paintingMediumLengthLength
Points to noteNot recommended for ground installationNot good at curved surfacesNot good at special shapesNot good at wet areas

Description: The values in the table above are common ranges for various materials, used to illustrate applicable boundaries and not constituting a ranking of any material. For this project, printed slate flexible stone was ultimately selected because blue-gray Yunlong slate is laid continuously along the corridor, with light strips concealed in the skirting to wash the wall.

2.0 Why is printed slate flexible stone

Hotel corridors are spaces of "repeated viewing"—guests pass through every day, and any misaligned seam will be seen repeatedly. The blue-gray tone of Yunlong slate has stable layering under wall-washing light strips, and the material can be bent and applied as a whole piece on the curved wall at the end of the corridor, avoiding dense diagonal seams on the curved surface; the volume of 5 floors × 96 rooms in the corridor also requires the material to be supplied in batches by floor.

2.1 Three questions for selection

Condense the selection into three questions, and the direction can basically be set:

  1. Is the wall curved or column-shaped? Yes → prioritize flexible materials that can bend; No → then compare weight and construction period.
  2. Can the substrate bear the weight of the stone? Cannot (lightweight partition walls, old walls, insulated walls) → prioritize flexible materials; can → natural stone is also an option.
  3. What kind of atmosphere does the space want? The dark metal edge trim runs parallel to the slate bedding direction, making the facade cleaner.

Answers to the three questions for this project: the blue-gray Yunlong slate runs throughout the corridor, with the light strip concealed in the skirting to wash the wall; the curved wall at the end of the corridor is fully wrapped with a single curved piece, avoiding dense joints; the dark metal edge trim runs parallel to the slate bedding direction, making the facade cleaner. Therefore, printed slate flexible stone was chosen.

3. Configuration plan

3.1 Material specifications and packaging

Specifications (mm) Thickness (mm) Approx. weight per panel (kg) Wooden crate packaging (pieces/crate) Area of wooden crate after packaging (㎡) Weight after packaging approx. (kg)
600×12002.3–2.82.5–2.8330237.6900
1200×30002.3–2.815–15.5802881200

Optional colors: gray, white, black (other colors can be customized).

Texture and light perception notes: The bedding planes and fissure directions of slate are random, so regular repetition will not appear on the same wall.

3.2 Allocation by space

Different parts of the same project do not have the same requirements for materials. The table below breaks down the actual space of a business hotel and explains why each part is specified this way.

Space / Location Area share ★ Material usage Why set it this way?
Main viewing surface (the first wall directly facing you when entering)20% or soFull-piece laying, seams kept away from the centerWhere the line of sight rests longest, the overall appearance is most complete
Side walls and passagewaysabout 35%Conventional installation, with joints aligned continuouslyLarge area, with the focus on smooth, continuous seams
Curved wall / partitionabout 15%Full-piece curved wrappingPiecing curved surfaces into small pieces creates dense diagonal seams
Column wrappingabout 8%%Full-piece wrapping on the column surface, with seams kept at the sides and rearThe key is that no seams are visible from the front
Door openings and window casingsabout 10%Use matching termination pieces; do not butt-join on siteCut edges easily expose the panel backing
Form and local areasAbout 12%%Custom-shaped panels according to drawingsOn-site cutting precision for irregular pieces is insufficient

★Description: The proportions in the table above are common distributions for similar restaurant/hotel spaces and are used to estimate material quantities for each part; actual quantities are subject to on-site measurement and layout drawings.

3.3 Estimation of Quantity and Construction Schedule

The calculation process is given below so it can be reviewed according to your own project's basis.

Project Calculation formula Result
Net installation areaOn-site measurement (including public areas)Approx. 2,150 ㎡
Material preparation area2150 × (1 + 12% loss)Approx. 2408 ㎡
Number of wooden crates2408 ÷ 237.6 m²/box, rounded upApprox. 11 boxes
Substrate treatmentLeveling, repair, primer2–3 working days
Layout setting-outSnap lines, align seams, set the starting point1-2 working days
Adhesive mounting6 people per group, average daily area of 60-100 ㎡ ★Approx. 30 working days
Finishing and acceptanceEdge trim, cleaning, acceptance1-2 working days
TotalConfigure for 6 people34 working days

3.4 Material List

Auxiliary materials Purpose Description
Special adhesiveMain material for full-surface bonding methodSelect according to product instructions; use weather-resistant type for outdoor or damp areas
Interface agentSubstrate sealingSelect according to substrate material
Edge trim / internal and external corner piecesCorners and closuresSame color family as the main material; prioritize matching accessories rather than on-site cutting
Joint filler materialJoint sealingClose to the main material color number to avoid overly prominent joint lines
DetergentCompletion cleaningNeutral cleaner; strong acids and alkalis prohibited

IV. Construction process and acceptance control points: on-site method for "Printed Slate Flexible Stone"

4.1 Seven steps

  1. Substrate inspection: Moisture content, flatness, and strength must all pass. Flatness is checked with a 2 m straightedge; sanding and loose layers must be removed down to a solid substrate, and hollow areas must be knocked out and redone.
  2. Substrate treatment: Walls with high moisture content require a sealing primer first; different interface agents are selected for different substrates.
  3. Layout setting-out: Put the layout plan on paper before starting work; mark door and window openings, switches, sockets, and internal/external corner positions; align seam lines across different walls in the same space where possible.
  4. Cutting processing: Cut to layout dimensions; cover cut edges with trim or pressure strips; determine opening positions at the layout stage.
  5. Full bonding installation: The full-surface bonding method is recommended, starting from the main viewing face and progressing to both sides and upward; apply along the arc direction at curved areas.
  6. Finishing treatment: Internal and external corners use matching trim pieces; junctions with door frames, ceilings, and floors are executed according to the node drawings.
  7. Cleaning acceptance: Use a neutral cleaner to remove residual adhesive and fingerprints, and check item by item according to the acceptance checklist.

4.2 Acceptance Control Sheet

Inspection items Control points Criterion
Substrate flatness2 m straightedge inspectionGap not exceeding 3mm ★
Substrate moisture contentSeal damp areas firstNo obvious moisture marks, no water seepage
Joint line alignmentAlign joint lines within the same spaceSmooth and free of steps by visual inspection
Curved-surface installationDirection along the arcNo obvious sharp folds, no edge lifting
External corner closureUse matching termination piecesNo exposed board bottom, consistent color
HollowingSpot-check by tapping each pieceHollowing rate not exceeding 5% ★
Surface cleaningNeutral cleanerNo residual glue, no scratches

The specific allowable deviation values shall be subject to the standards and contract terms of the project location; the table above shows the common industry practice ranges.

4.3 Special methods for arc and column

Curved walls, columns and irregular corners are where flexible materials differ most directly from traditional finishes. There are several points that must be confirmed in advance for the installation method:

Location The method. Items to confirm in advance
Large-radius curved wall (R ≥ 2m)Full-piece curved application, seam following the curve directionArc radius, panel thickness, ambient temperature
Small-radius curved wall (R < 2m)Test the bend first; when there is obvious springback, switch to narrow-strip splicingMust first test bending with a physical mock-up
Cylindrical column claddingFull-piece wrapping, seam left at the side rearColumn diameter and whether there are embedded parts on the column surface
Arches and door openingsContinuous curve, use matching termination piecesDoor opening squareness
Internal and external cornersUse matching termination pieces; do not butt-join on siteWhether the color of finishing pieces is consistent with the main material

4.4 Common problems and avoidance

Phenomenon Reason Workaround
Joint misalignmentUneven substrate, cumulative error block by blockFirst snap lines to control continuous joints, and start installation from the main sightline
Curved-surface edge liftingRadius smaller than the material's usable rangeTest bending before installation to confirm; change to narrower strips if necessary
External corner showing through to the substrateOn-site cutting and butt-joiningUse matching inner and outer corner pieces
The light strip reveals the jointsJoint conflicts with the position of the light stripDetermine the joints together with the light strips during the layout stage
Color difference concentrationMixing different batchesOrder enough at once for the same batch, and mix materials before installation
HollowingBase-layer sanding and insufficient adhesive dosageSubstrate treatment in place, full-adhesion installation

4.5 Construction tools and personnel allocation

Project Configuration Description
Measuring tools2 m straightedge, level, tape measure, chalk lineBase-layer acceptance and chalk-line layout
Cutting toolsUtility knife / board cutting knife, straight rulerOn-site cutting according to layout dimensions
Mixing toolsElectric mixerMix the adhesive according to the specified ratio
Adhesive application toolsNotched trowelFull-surface bonding method: control consistent adhesive layer thickness
Compaction toolPressure roller / rubber malletRemove air bubbles and ensure full adhesion
Cleaning toolsSoft cloth, neutral cleanerCompletion cleaning
StaffingAdhesive mounting, 2–4 people per team ★This project is staffed with 6 people
Daily production capacity per group60–100 square meters per group ★Related to substrate conditions and modeling complexity

★Description: Staffing and daily capacity are common industry ranges, used to estimate the construction period; actual efficiency is affected by substrate conditions, shape complexity, floor height and on-site access conditions.

V. Image display and application description

5.1 Elevator Hall

Elevator lobby, gray-white wavy stone-grain wall and metal door leaves
Figure 1 · Elevator hall, gray-white wave-pattern stone-texture wall and metal doors

5.2 Window-side Resting Corner

Window-side lounge corner, gray-white wavy stone-pattern feature wall and sofa
Figure 2 · Window-side rest corner, gray-white wavy stone-pattern background wall and sofa

5.3 Bar Area

Bar counter rest area, gray-white wavy stone-texture wall and counter body
Fig. 3 · Bar lounge area, gray-white wavy stone-texture wall and counter body

5.4 Dining booth

Dining booth, gray-white wavy stone-texture backdrop wall with tables and chairs
Figure 4 · Dining banquette, gray-white wavy stone-grain feature wall with tables and chairs

5.5 Reception Area

Reception area, gray-white wavy stone-texture background wall and curved front desk
Figure 5 · Reception area, gray-white wavy stone-pattern background wall and curved front desk

5.6 Indoor Swimming Pool

Indoor pool, gray-white curved stone-veined wall with waterside lounge chairs
Figure 6 · Indoor pool, gray-white curved stone-texture wall and waterside lounge chairs

5.7 Resting space

Rest space, gray-white curved stone-textured wall and single sofa
Figure 7 · Rest space, gray-white curved stone-texture wall and armchair

5.8 Round Dining Area

Round-table dining area, gray-white stone-texture curved partition wall and pendant light
Figure 8 · Round-table dining area, gray-white stone-texture curved partition wall and pendant lights

5.9 Bedroom

Bedroom, gray-white wavy stone-texture headboard wall with bed
Figure 9 · Bedroom, gray-white wavy stone-texture headboard wall and bed

5.10 Tall reception area

Full-height reception area, gray-white wavy stone-texture wall and fireplace
Figure 10 · Double-height reception area, gray-white wave-pattern stone-texture wall and fireplace

5.11 Bedroom close-up

Bedroom close-up, gray-white stone-look background and bedside shelving
Figure 11 · Bedroom close-up, gray-white stone-texture backdrop and bedside shelving

5.12 Bar

Bar counter, gray-white wavy stone-texture counter body and illuminated wine and beverage shelving
Figure 12 · Bar counter, gray-white wavy stone-pattern counter body and illuminated liquor shelf

5.13 Another perspective of the bedroom

Another view of the bedroom, gray-white wavy stone-look headboard background
Figure 13 · Another view of bedroom, gray-white wavy stone-pattern headboard background

VI. Communication and confirmation process

The following are several questions confirmed by both parties during material selection and construction, organized in the order of the conversation.

  • Hotel side: The corridor has 5 floors and 96 rooms, and the schedule is very tight; can material supply be guaranteed?
  • Our side: It can be shipped in batches by floor. Ship two floors first, then arrange the rest according to your construction progress, without occupying on-site storage.
  • Design party: The wall at the end of the corridor is curved with a radius of about 1.2 meters; does it need to be divided into strips?
  • Our side: for 1.2 meters, it is recommended to first take a sample and test bending. If springback is obvious, narrow-strip assembly is more stable, and seams running along the curve actually look better.
  • Construction party: If the light strip is to be hidden in the baseboard and wash upward onto the wall, will it reveal the seams?
  • Our side: Yes. Therefore, when laying out, offset the joints outside the 150mm range directly above the light strip, or make the joints parallel to the light strip at a consistent distance, so the wash of light is even.
  • Hotel side: How is the moisture resistance? The ring of wall outside the restroom also needs to be covered.
  • Our side: The material itself does not absorb water, so it can be used directly in dry areas; in wet areas, it is recommended to leave out the shower partition zone, following the dry/wet zoning plan.

Scope statement: The above is a written summary of the communication content, used to explain the decision-making process; it does not represent a commitment to results, and the contract terms and on-site conditions shall prevail.

Seven, usage effects and daily maintenance

7.1 Perception and light environment

The bedding planes and fissure directions of slate are random, so regular repetition will not appear on the same wall. The same wall looks different under different color temperatures: warmer under warm light and more neutral under cool light—this is also why we recommend requesting physical samples first and comparing them under actual lighting.

7.2 Daily maintenance

Project The method. Note
Daily cleaningWipe with clean water or neutral detergentDo not use strong acids or strong alkalis
Oil stain treatmentNeutral cleaner + soft clothDo not use steel wool
Localized damageIndividual panels can be replacedReplaceable conditions were retained during layout
Damp areasMaintain ventilationDoes not absorb water, does not swell
Outdoor areasRegular washingExecute according to the design scope

7.3 Post-delivery Recheck Sheet

Review items Suggested timing Points of concern
Joints and closures7 days after handoverWhether there is lifting or cracking
Hollowing30 days after handoverSampling and tapping inspection
Color consistency30 days after handoverComparison across different walls and different floors
Cleaning statusDailyWhether there are stubborn stains

7.4 Intersection with Adjacent Materials

Wall materials rarely exist alone; there will always be neighbors such as ceilings, floors, wood veneer, metal parts and glass. How well the junctions are handled directly determines whether the elevation looks "clean" or "fragmented."

Adjacent materials Transition method Note
Ceiling / suspended ceilingPress the edge with a top trim strip, or leave a 3–5 mm revealJoint width must be consistent over the full length
Floor / skirtingSkirting line presses the lower edge of the panelDo not let the bottom edge sit directly on the floor, to avoid dragging wear
Wood finishTransition within the same color family, with the joint left at an internal cornerPlacing the two materials on the same wall requires comparing color differences first
Metal edge trim stripMetal strips press the seam, with the direction parallel to the grain directionColors are mainly matte dark tones to avoid stealing the show
Glass partitionUse a pressure strip for finishing, leaving a caulking gap between the glass and the panelCut edges of the panel need to be covered with trim
Door and window casingsUse matching termination pieces; do not butt-join on siteDoor opening squareness directly affects the finishing result

7.5 Cost Estimation

The cost of a wall consists of three parts: main material + auxiliary materials + labor. The budget estimate basis is as follows (◆budget estimate, not an actual measured bill):

Composition Scope Influencing factors
Main material.Preparation area approx. 2408 ㎡ ÷ 237.6 ㎡ per boxColor, thickness, specifications, batch
Auxiliary materialsAdhesive + primer + trim pieces + groutSubstrate conditions, termination complexity
ManualMounting area × labor cost per unit areaForm complexity, floor height, proportion of special shapes

◆Estimate: Specific unit prices vary with pattern, thickness, order quantity, and construction conditions; a wide range is normal. This article does not provide a single quotation to avoid misleading; for project pricing, please provide the area, pattern, and delivery location.

VIII. Common questions (FAQ)

Below are the questions most frequently asked about material selection and construction in this project.

Is Printed Slate Flexible Stone suitable for spaces such as hotel corridors?

Suitable. The bedding and fissure directions of the slate are random, so no regular repetition appears on the same wall. This project uses it for the hotel corridor, elevator lobby, guest rooms and dry areas of the restrooms. The blue-gray Yunlong slate is laid throughout the corridor, with light strips concealed at the baseboard for wall washing.

Can curved walls and column cladding be done in one continuous piece?

Yes. The material has a certain flexibility and can be bent within a certain radius, so columns, curved walls and irregular corners can achieve full-panel wrapping with continuous seams. The specific usable radius depends on the selected model, thickness and substrate conditions; it is recommended to first test-bend a physical sample at the corresponding curvature to confirm.

How long does the schedule generally take?

This project is approximately 2150 ㎡, staffed with 6 people, and completed in 34 working days (including substrate preparation and finishing). The installation itself accounts for about 30 working days, with the remainder for substrate work, layout marking, and acceptance inspection. The main variable in the schedule is substrate condition—substrate rework will directly eat into the time saved on installation.

Can it be used in damp areas?

Yes. The material itself does not absorb water, and after construction the wall surface is not prone to dampness or mildew, so it can be used in humid environments and underground spaces. For wet areas such as bathrooms, it is recommended to confirm the specific scope in conjunction with the wet/dry zoning plan.

What about fire performance?

The material has flame-retardant properties; the specific combustion performance ratingshall be in accordance with the valid inspection report of the selected model. If the project has specific requirements for fire rating, please specify before placing an order.

How much difference in texture is there compared to natural stone?

Differences are visible up close: natural stone has naturally occurring random variation, while the texture of Printed Slate flexible stone is formed by embossing or printing, giving greater consistency within the same product. From a distance the overall look is similar. When placing natural stone and flexible materials on adjacent walls in the same space, it is advisable to make a small sample comparison first.

Can old walls be renovated by direct pasting?

If the original wall surface is firm and has no hollowing, it is possible; old tile surfaces can also be covered directly. But before construction, each surface must be checked for hollowing, and hollowed areas must be knocked out and redone—this step cannot be skipped.

Does the material have test reports? What standard does it follow?

Execution JG/T 540-2017 'Building Flexible Stone-faced Decorative Material' (issued by the Ministry of Housing and Urban-Rural Development). Environmental protection and combustion performance test reports for the corresponding models can be provided with the goods.

How to confirm color and texture?

It is advisable to request physical samples and compare them under the project's actual lighting before deciding the color number. There are differences between screen display and actual materials; in particular, stone-texture materials look different at different angles and color temperatures.

Can a single damaged panel be replaced later?

Yes. During layout, the seam lines and termination positions have already been determined, and a single piece can be pried out from the termination for replacement. It is recommended to reserve 1–2 boxes of same-batch material as spares at delivery.

IX. Project File and Contact Information

Project Content
Project nameHotel corridor wall material—Printed slate (Yunlong) flexible stone application case (Ziyang)
LocationZiyang City, Sichuan Province
Main material.Printed Slate Flexible Stone (Yunlong)
Material seriesSlate and Natural Mountain Stone series
Construction areaApprox. 2,150 ㎡
Schedule34 working days
Related sectionsProject Cases · Hotel corridor
Implementation standardsJG/T 540-2017

Similar projects can be found in the Project Cases column; for material specifications and colors see the Slate and Natural Mountain Stone series.


Legend and specification notes

  • ★Project experience = Industry common practice and experience range, not a reference for national standard data.
  • ◆Estimate = Estimated value calculated based on the scale,not an actual measured bill; actual conditions are subject to the contract agreement and site conditions.
  • Material parameters are taken from the corresponding product file; combustion performance, environmental grade, etc. are subject to the valid test report for the selected model.
  • Area, schedule, and quantity are estimates based on industry-scale figures; the calculation process is provided and can be reviewed against your own project's basis.

Find the appropriate wall expression for your project.

Provide the type of space, wall area, and design intention. Communicate about materials, samples, and quotations.

Consulting project material selection ↗
Contact phone number Product Catalog Free Sample
WeChat ID copied