Business hotel 1780㎡ new line stone (Thousand-layer Wood) wall construction case
The business hotel project is located in Mianyang City, Sichuan Province, and the main wall material is new line stone flexible stone (Thousand-layer Wood), used for hotel corridors, elevator lobbies and guest room corridor end walls. The construction area is about 1780 ㎡ (including public areas), completed by 5 people in 29 working days.
Introduction
The business hotel project is located in Mianyang City, Sichuan Province, and the main wall material is New Line Stone Flexible Stone (thousand-layer wood), used for hotel corridors, elevator lobbies and guest room corridor end walls, with a construction area of about 1780 ㎡ (including public areas), completed by 5 people in 29 working days. This article explains the material selection basis, quantity and schedule estimates, construction control points, application images and common questions all at once.
- Project: Business hotel · Hotel corridors, elevator lobbies, and guest room corridor end walls
- Location: Mianyang City, Sichuan Province
- Main material: Xin Xian Shi flexible stone (thousand-layer wood)
- Construction area: Approx. 1780 ㎡
- Schedule: 29 working days / 5 people
- Implementation standards: JG/T 540-2017
Project file
| Project | Content |
|---|---|
| Project name | Hotel corridor wall material—New line stone flexible stone application case (Mianyang) |
| Space type | Hotel corridor |
| Business type | Business hotel |
| City | Mianyang City, Sichuan Province |
| Scale | 84 guest rooms + corridors on 4 floors |
| Construction location | Hotel corridor, elevator lobby and guest room corridor end walls |
| Main material. | New Line Stone flexible stone (Thousand-Layer Wood) |
| Construction area | Approx. 1,780 ㎡ (including common areas) |
| Construction period | 29 working days |
| Number of construction workers | 5 people |
| Implementation standards | JG/T 540-2017"Flexible Stone-like Facing Materials for Buildings" |
1. Customer industry usage scenario: the real wall requirements of a business hotel
- Low clear-height corridors need to "look taller" A clear height of 2.7 m is on the low side for a hotel corridor, and it feels even more compressed once pipes are concealed in the ceiling. Vertical lines are the most direct visual way to increase perceived height, yet cost less than adjusting the ceiling or changing the structure.
- Large panels reduce horizontal joints Corridor walls are very long, and small-format panels create dense horizontal joints, cutting the elevation into fragments. 1180×2640 large panels can significantly reduce the number of joints, making joint management easier.
- IV. Material batch consistency across four floors This item covers 84 guest rooms and 4 floors of corridors. Ordering the full quantity in one batch is the most reliable approach; if it must be split into batches, mix the materials before installation to spread any possible color difference across different floors.
- The elevator lobby is a high-risk point where "two batches of material meet" Materials for the elevator lobby often come from different batches. If there is a color difference, it will show up here first. The approach is to reserve the elevator lobby materials from the same box, store them separately, and install them last.
- Continuity of column wrapping and corners There are structural columns and corners in the corridor. Column surfaces are wrapped with the same material, with joints aligned to adjacent walls; corners can be bent over as a single piece or transitioned with trim strips, depending on the corner radius.
- Public areas with high cleaning frequency Corridors are one of the areas cleaned most frequently, and the walls are wiped repeatedly. A dense surface and scrub resistance are basic requirements, while cleaning methods that would damage the texture must be avoided.
II. Material comparison: why choose "New Vein Stone flexible stone"
When comparing wall materials side by side, what really determines the selection is often not "which one looks better," but rather whether the base layer can bear the load, whether the schedule can be compressed, and whether the shape can be achieved.
| Comparison item | New Line Stone flexible stone | Tile / Slab. | Natural stone. | Traditional wood veneer |
|---|---|---|---|---|
| Weight per square meter | Approx. 4.0–4.5 kg/㎡ | Noticeably heavier, substrate reinforcement required | Heaviest; mostly requires dry hanging | Includes thicker base coat |
| thickness | 2.5–3.5 mm | 6–12 mm | 15–30 mm | Includes base coat 15 mm or more |
| Curved surface and column | Can be curved within a certain radius, covering the entire surface | Small pieces must be cut and pieced together, with dense joints | Requires waterjet processing; cost and lead time increase | Requires steam heat bending or slitting |
| Construction method | No skeleton required, full adhesion after leveling the base | Special adhesive, high requirements for joint-gap process | Mostly dry-hung, requires embedded parts | Requires furring strips or a backing board |
| Moisture-proof and mold-proof | Does not absorb water, does not swell | It does not absorb water itself, but dirt easily collects in the seams | Some stone absorbs water | Prone to swelling and mold when damp |
| Schedule | Short, no wet work or painting | Medium | Length | Length |
| Points to note | Not recommended for ground installation | Not good at curved surfaces | Not good at special shapes | Not good at wet areas |
Description: The values in the table above are common ranges for various materials, used to illustrate applicable boundaries and not constituting a ranking of any material. For this project, New Line Stone flexible stone was ultimately selected because the vertical stone lines of line stone are laid continuously along the corridor, visually raising the ceiling height.
2.0 Why choose new line stone flexible stone
The corridor clear height is only 2.7 m; vertical installation can visually raise the ceiling height, which is the first determining factor beyond material selection. The texture of Qiancengmu New Line Stone consists of fine, elongated, consistently oriented stone lines; after vertical arrangement, they create an upward visual guide; the 1180×2640 large panels can also reduce horizontal joints, making the corridor elevation more complete.
2.1 Three questions for selection
Condense the selection into three questions, and the direction can basically be set:
- Is the wall curved or column-shaped? Yes → prioritize flexible materials that can bend; No → then compare weight and construction period.
- Can the substrate bear the weight of the stone? Cannot (lightweight partition walls, old walls, insulated walls) → prioritize flexible materials; can → natural stone is also an option.
- What kind of atmosphere does the space want? Use the same batch for the elevator lobby and corridor to avoid color differences across areas.
Answers to the three questions for this project: the vertical stone lines of the line stone run throughout the corridor, visually raising the ceiling height; the 1180×2640 large panels reduce horizontal joints, making the corridor facade more complete; the elevator lobby and corridor use the same batch, avoiding color differences across areas. Therefore, new-line stone flexible stone was chosen.
3. Configuration plan
3.1 Material specifications and packaging
| Specifications (mm) | Thickness (mm) | Approx. weight per panel (kg) | Wooden crate packaging (pieces/crate) | Area of wooden crate after packaging (㎡) | Weight after packaging approx. (kg) |
|---|---|---|---|---|---|
| 1180×2640 | 2.5–3.5 | 14 | 70 | 218 | 1000 |
Optional colors: white, black (other colors can be customized).
Texture and light perception notes: The texture of line stone consists of fine, elongated stone lines running in a consistent direction; vertical installation can visually raise the ceiling height.
3.2 Allocation by space
Different parts of the same project do not have the same requirements for materials. The table below breaks down the actual space of a business hotel and explains why each part is specified this way.
| Space / Location | Area share ★ | Material usage | Why set it this way? |
|---|---|---|---|
| Main viewing surface (the first wall directly facing you when entering) | 20% or so | Full-piece laying, seams kept away from the center | Where the line of sight rests longest, the overall appearance is most complete |
| Side walls and passageways | about 35% | Conventional installation, with joints aligned continuously | Large area, with the focus on smooth, continuous seams |
| Curved wall / partition | about 15% | Full-piece curved wrapping | Piecing curved surfaces into small pieces creates dense diagonal seams |
| Column wrapping | about 8%% | Full-piece wrapping on the column surface, with seams kept at the sides and rear | The key is that no seams are visible from the front |
| Door openings and window casings | about 10% | Use matching termination pieces; do not butt-join on site | Cut edges easily expose the panel backing |
| Form and local areas | About 12%% | Custom-shaped panels according to drawings | On-site cutting precision for irregular pieces is insufficient |
★Description: The proportions in the table above are common distributions for similar restaurant/hotel spaces and are used to estimate material quantities for each part; actual quantities are subject to on-site measurement and layout drawings.
3.3 Estimation of Quantity and Construction Schedule
The calculation process is given below so it can be reviewed according to your own project's basis.
| Project | Calculation formula | Result |
|---|---|---|
| Net installation area | On-site measurement (including public areas) | Approx. 1,780 ㎡ |
| Material preparation area | 1780 times (1 + 12% loss) | Approx. 1,993 ㎡ |
| Number of wooden crates | 1993 divided by 218 square meters per case, rounded up | Approx. 10 boxes |
| Substrate treatment | Leveling, repair, primer | 2–3 working days |
| Layout setting-out | Snap lines, align seams, set the starting point | 1-2 working days |
| Adhesive mounting | 5 people in a group, average daily 60-100 ㎡ ★ | Approx. 25 working days |
| Finishing and acceptance | Edge trim, cleaning, acceptance | 1-2 working days |
| Total | Configure for 5 people | 29 working days |
3.4 Material List
| Auxiliary materials | Purpose | Description |
|---|---|---|
| Special adhesive | Main material for full-surface bonding method | Select according to product instructions; use weather-resistant type for outdoor or damp areas |
| Interface agent | Substrate sealing | Select according to substrate material |
| Edge trim / internal and external corner pieces | Corners and closures | Same color family as the main material; prioritize matching accessories rather than on-site cutting |
| Joint filler material | Joint sealing | Close to the main material color number to avoid overly prominent joint lines |
| Detergent | Completion cleaning | Neutral cleaner; strong acids and alkalis prohibited |
IV. Construction process and acceptance control points: on-site method for "New Line Stone Flexible Stone"
4.1 Seven steps
- Substrate inspection: Moisture content, flatness, and strength must all pass. Flatness is checked with a 2 m straightedge; sanding and loose layers must be removed down to a solid substrate, and hollow areas must be knocked out and redone.
- Substrate treatment: Walls with high moisture content require a sealing primer first; different interface agents are selected for different substrates.
- Layout setting-out: Put the layout plan on paper before starting work; mark door and window openings, switches, sockets, and internal/external corner positions; align seam lines across different walls in the same space where possible.
- Cutting processing: Cut to layout dimensions; cover cut edges with trim or pressure strips; determine opening positions at the layout stage.
- Full bonding installation: The full-surface bonding method is recommended, starting from the main viewing face and progressing to both sides and upward; apply along the arc direction at curved areas.
- Finishing treatment: Internal and external corners use matching trim pieces; junctions with door frames, ceilings, and floors are executed according to the node drawings.
- Cleaning acceptance: Use a neutral cleaner to remove residual adhesive and fingerprints, and check item by item according to the acceptance checklist.
4.2 Acceptance Control Sheet
| Inspection items | Control points | Criterion |
|---|---|---|
| Substrate flatness | 2 m straightedge inspection | Gap not exceeding 3mm ★ |
| Substrate moisture content | Seal damp areas first | No obvious moisture marks, no water seepage |
| Joint line alignment | Align joint lines within the same space | Smooth and free of steps by visual inspection |
| Curved-surface installation | Direction along the arc | No obvious sharp folds, no edge lifting |
| External corner closure | Use matching termination pieces | No exposed board bottom, consistent color |
| Hollowing | Spot-check by tapping each piece | Hollowing rate not exceeding 5% ★ |
| Surface cleaning | Neutral cleaner | No residual glue, no scratches |
The specific allowable deviation values shall be subject to the standards and contract terms of the project location; the table above shows the common industry practice ranges.
4.3 Special methods for arc and column
Curved walls, columns and irregular corners are where flexible materials differ most directly from traditional finishes. There are several points that must be confirmed in advance for the installation method:
| Location | The method. | Items to confirm in advance |
|---|---|---|
| Large-radius curved wall (R ≥ 2m) | Full-piece curved application, seam following the curve direction | Arc radius, panel thickness, ambient temperature |
| Small-radius curved wall (R < 2m) | Test the bend first; when there is obvious springback, switch to narrow-strip splicing | Must first test bending with a physical mock-up |
| Cylindrical column cladding | Full-piece wrapping, seam left at the side rear | Column diameter and whether there are embedded parts on the column surface |
| Arches and door openings | Continuous curve, use matching termination pieces | Door opening squareness |
| Internal and external corners | Use matching termination pieces; do not butt-join on site | Whether the color of finishing pieces is consistent with the main material |
4.4 Common problems and avoidance
| Phenomenon | Reason | Workaround |
|---|---|---|
| Joint misalignment | Uneven substrate, cumulative error block by block | First snap lines to control continuous joints, and start installation from the main sightline |
| Curved-surface edge lifting | Radius smaller than the material's usable range | Test bending before installation to confirm; change to narrower strips if necessary |
| External corner showing through to the substrate | On-site cutting and butt-joining | Use matching inner and outer corner pieces |
| The light strip reveals the joints | Joint conflicts with the position of the light strip | Determine the joints together with the light strips during the layout stage |
| Color difference concentration | Mixing different batches | Order enough at once for the same batch, and mix materials before installation |
| Hollowing | Base-layer sanding and insufficient adhesive dosage | Substrate treatment in place, full-adhesion installation |
4.5 Construction tools and personnel allocation
| Project | Configuration | Description |
|---|---|---|
| Measuring tools | 2 m straightedge, level, tape measure, chalk line | Base-layer acceptance and chalk-line layout |
| Cutting tools | Utility knife / board cutting knife, straight ruler | On-site cutting according to layout dimensions |
| Mixing tools | Electric mixer | Mix the adhesive according to the specified ratio |
| Adhesive application tools | Notched trowel | Full-surface bonding method: control consistent adhesive layer thickness |
| Compaction tool | Pressure roller / rubber mallet | Remove air bubbles and ensure full adhesion |
| Cleaning tools | Soft cloth, neutral cleaner | Completion cleaning |
| Staffing | Adhesive mounting, 2–4 people per team ★ | This project is staffed with 5 people |
| Daily production capacity per group | 60–100 square meters per group ★ | Related to substrate conditions and modeling complexity |
★Description: Staffing and daily capacity are common industry ranges, used to estimate the construction period; actual efficiency is affected by substrate conditions, shape complexity, floor height and on-site access conditions.
V. Image display and application description
5.1 Guest Room Corridor
5.2 Elevator hall
5.3 Corridor end scene
5.4 Guest room entrance
5.5 Indoor Corridor
5.6 Rest Corner
5.7 Elevator Hall Another Perspective
VI. Communication and confirmation process
The following are several questions confirmed by both parties during material selection and construction, organized in the order of the conversation.
- Design party: The corridor ceiling height is only 2.7 meters, and we want it to look taller.
- Our side: Vertical laying is recommended. The texture direction of linear stone is consistent, and vertical arrangement creates an upward visual guide, making it look taller than horizontal laying.
- Hotel side: On the fourth-floor corridor, will the material have color differences?
- Our side: It is recommended to order enough in a single batch and mix materials once before laying, spreading color differences across different floors.
- Construction party: for 1180×2640 panels, how do you get around corridor corners?
- Our side: Use trim strips at corners, or bend the panel around. A single large panel running around the corner gives the best effect, but the corner radius must be confirmed first.
Scope statement: The above is a written summary of the communication content, used to explain the decision-making process; it does not represent a commitment to results, and the contract terms and on-site conditions shall prevail.
Seven, usage effects and daily maintenance
7.1 Perception and light environment
The texture of Line Stone consists of fine, elongated, uniformly oriented stone lines; vertical installation can visually raise the ceiling height. The same wall looks different under different color temperatures: warmer under warm light and more neutral under cool light, which is also why we recommend requesting a physical sample first and comparing it under actual lighting.
7.2 Daily maintenance
| Project | The method. | Note |
|---|---|---|
| Daily cleaning | Wipe with clean water or neutral detergent | Do not use strong acids or strong alkalis |
| Oil stain treatment | Neutral cleaner + soft cloth | Do not use steel wool |
| Localized damage | Individual panels can be replaced | Replaceable conditions were retained during layout |
| Damp areas | Maintain ventilation | Does not absorb water, does not swell |
| Outdoor areas | Regular washing | Execute according to the design scope |
7.3 Post-delivery Recheck Sheet
| Review items | Suggested timing | Points of concern |
|---|---|---|
| Joints and closures | 7 days after handover | Whether there is lifting or cracking |
| Hollowing | 30 days after handover | Sampling and tapping inspection |
| Color consistency | 30 days after handover | Comparison across different walls and different floors |
| Cleaning status | Daily | Whether there are stubborn stains |
7.4 Intersection with Adjacent Materials
Wall materials rarely exist alone; there will always be neighbors such as ceilings, floors, wood veneer, metal parts and glass. How well the junctions are handled directly determines whether the elevation looks "clean" or "fragmented."
| Adjacent materials | Transition method | Note |
|---|---|---|
| Ceiling / suspended ceiling | Press the edge with a top trim strip, or leave a 3–5 mm reveal | Joint width must be consistent over the full length |
| Floor / skirting | Skirting line presses the lower edge of the panel | Do not let the bottom edge sit directly on the floor, to avoid dragging wear |
| Wood finish | Transition within the same color family, with the joint left at an internal corner | Placing the two materials on the same wall requires comparing color differences first |
| Metal edge trim strip | Metal strips press the seam, with the direction parallel to the grain direction | Colors are mainly matte dark tones to avoid stealing the show |
| Glass partition | Use a pressure strip for finishing, leaving a caulking gap between the glass and the panel | Cut edges of the panel need to be covered with trim |
| Door and window casings | Use matching termination pieces; do not butt-join on site | Door opening squareness directly affects the finishing result |
7.5 Cost Estimation
The cost of a wall consists of three parts: main material + auxiliary materials + labor. The budget estimate basis is as follows (◆budget estimate, not an actual measured bill):
| Composition | Scope | Influencing factors |
|---|---|---|
| Main material. | Preparation area approx. 1993 ㎡ ÷ 218 ㎡ per box | Color, thickness, specifications, batch |
| Auxiliary materials | Adhesive + primer + trim pieces + grout | Substrate conditions, termination complexity |
| Manual | Mounting area × labor cost per unit area | Form complexity, floor height, proportion of special shapes |
◆Estimate: Specific unit prices vary with pattern, thickness, order quantity, and construction conditions; a wide range is normal. This article does not provide a single quotation to avoid misleading; for project pricing, please provide the area, pattern, and delivery location.
VIII. Common questions (FAQ)
Below are the questions most frequently asked about material selection and construction in this project.
Is New Line Stone flexible stone suitable for spaces such as hotel corridors?
Suitable. The texture of Line Stone consists of fine, elongated stone lines with a consistent direction, and vertical laying can visually raise the ceiling height. This project uses it for the hotel corridor, elevator lobby and guest room corridor end walls. The vertical stone lines of Line Stone are laid throughout the corridor, visually raising the ceiling height.
Can curved walls and column cladding be done in one continuous piece?
Yes. The material has a certain flexibility and can be bent within a certain radius, so columns, curved walls and irregular corners can achieve full-panel wrapping with continuous seams. The specific usable radius depends on the selected model, thickness and substrate conditions; it is recommended to first test-bend a physical sample at the corresponding curvature to confirm.
How long does the schedule generally take?
This project is approximately 1780 ㎡, staffed with 5 people, and completed in 29 working days (including substrate preparation and finishing). The installation itself accounts for about 25 working days, with the remainder for substrate work, layout marking, and acceptance inspection. The main variable in the schedule is substrate condition—substrate rework will directly eat into the time saved on installation.
Can it be used in damp areas?
Yes. The material itself does not absorb water, and after construction the wall surface is not prone to dampness or mildew, so it can be used in humid environments and underground spaces. For wet areas such as bathrooms, it is recommended to confirm the specific scope in conjunction with the wet/dry zoning plan.
What about fire performance?
The material has flame-retardant properties; the specific combustion performance ratingshall be in accordance with the valid inspection report of the selected model. If the project has specific requirements for fire rating, please specify before placing an order.
How much difference in texture is there compared to natural stone?
Differences are visible up close: natural stone has naturally occurring random variation, while the texture of New Line Stone flexible stone is formed by embossing or printing, giving greater consistency within the same product. From a distance the overall look is similar. When placing natural stone and flexible materials on adjacent walls in the same space, it is advisable to make a small sample comparison first.
Can old walls be renovated by direct pasting?
If the original wall surface is firm and has no hollowing, it is possible; old tile surfaces can also be covered directly. But before construction, each surface must be checked for hollowing, and hollowed areas must be knocked out and redone—this step cannot be skipped.
Does the material have test reports? What standard does it follow?
Execution JG/T 540-2017 'Building Flexible Stone-faced Decorative Material' (issued by the Ministry of Housing and Urban-Rural Development). Environmental protection and combustion performance test reports for the corresponding models can be provided with the goods.
How to confirm color and texture?
It is advisable to request physical samples and compare them under the project's actual lighting before deciding the color number. There are differences between screen display and actual materials; in particular, stone-texture materials look different at different angles and color temperatures.
Can a single damaged panel be replaced later?
Yes. During layout, the seam lines and termination positions have already been determined, and a single piece can be pried out from the termination for replacement. It is recommended to reserve 1–2 boxes of same-batch material as spares at delivery.
IX. Project File and Contact Information
| Project | Content |
|---|---|
| Project name | Hotel corridor wall material—New line stone flexible stone application case (Mianyang) |
| Location | Mianyang City, Sichuan Province |
| Main material. | New Line Stone flexible stone (Thousand-Layer Wood) |
| Material series | Line Stone and Natural Texture Series |
| Construction area | Approx. 1,780 ㎡ |
| Schedule | 29 working days |
| Related sections | Project Cases · Hotel corridor |
| Implementation standards | JG/T 540-2017 |
Similar projects can be found at Project Cases View column; for material specifications and colors see Line Stone and Natural Texture Series.
Legend and specification notes
- ★Project experience = Industry common practice and experience range, not a reference for national standard data.
- ◆Estimate = Estimated value calculated based on the scale,not an actual measured bill; actual conditions are subject to the contract agreement and site conditions.
- Material parameters are taken from the corresponding product file; combustion performance, environmental grade, etc. are subject to the valid test report for the selected model.
- Area, schedule, and quantity are estimates based on industry-scale figures; the calculation process is provided and can be reviewed against your own project's basis.
Relevant Materials and Solutions
Flexible Stone Solutions Selection Guides Request sample quotationFind the appropriate wall expression for your project.
Provide the type of space, wall area, and design intention. Communicate about materials, samples, and quotations.