Wall construction case study: 1380㎡ coarse rammed earth (warm brown) for a mid-to-high-end hot pot restaurant

The mid-to-high-end hot pot restaurant project is located in Fuling District, Chongqing. The main wall material is coarse rammed earth flexible stone (warm brown), used for the walls of the hot pot restaurant's main hall, private rooms, corridors and rest area. The construction area is about 1380 ㎡, completed by 5 people in 23 working days.

Published time:

Introduction

The mid-to-high-end hot pot restaurant project is located in Fuling District, Chongqing. The main wall material is Coarse rammed earth Flexible Stone (warm brown), used for the walls of the main hall, private rooms, corridor, and lounge area of a hot pot restaurant, with a construction area of about 1380 ㎡, completed by 5 people in 23 working days. This article explains the material selection basis, quantity and schedule estimation, construction control points, application photos, and common questions all at once.

  • Project: Mid-to-high-end hot pot restaurant · hot pot restaurant main hall, private rooms, corridor and lounge walls
  • Location: Fuling District, Chongqing
  • Main material: Coarse rammed earth flexible stone (Warm Brown)
  • Construction area: Approx. 1380 ㎡
  • Schedule: 23 working days / 5 people
  • Implementation standards: JG/T 540-2017

Project file

Project Content
Project nameHot pot restaurant decoration material recommendation - Rammed earth board flexible stone multi-area application case (Fuling, Chongqing)
Space typeFood & Beverage Spaces
Business typeMid-to-high-end hot pot restaurant
CityFuling District, Chongqing
ScaleMain hall, 26 tables + 10 booth groups + 6 private rooms
Construction locationWalls of the hall, private rooms, corridors and rest areas in a hot pot restaurant
Main material.Coarse rammed earth flexible stone (warm brown)
Construction areaApprox. 1380㎡
Construction period23 working days
Number of construction workers5 people
Implementation standardsJG/T 540-2017"Flexible Stone-like Facing Materials for Buildings"

1. Customer industry usage scenario: the real wall requirements of a mid-to-high-end hot pot restaurant

  1. Multiple areas require a unified look. If the main hall, corridors, private rooms and lounge areas each use their own materials, guests will feel the disjointed sense of having "moved to a different place." Using the same material throughout and differentiating spatial character through furniture and lighting is the lowest-cost and most reliable approach.
  2. Private room partition walls cannot bear loads. The partition walls between private rooms are mostly lightweight blocks or light steel keel walls, which do not have conditions for dry hanging. The material's own weight is a hard constraint—this is also why natural stone is rarely used on private room walls.
  3. Fixing issues for wine cabinets and shelving. Wine cabinets and display racks must be fixed to the wall. Panels are applied over the substrate; conventional expansion fasteners can penetrate the panels into the substrate. The key is to reserve cabinet positions during layout to avoid fixation points landing exactly on panel seams.
  4. Moisture protection for the corridor and the outer wall of the restroom. The corridor of a hot pot restaurant is often adjacent to the restroom, and the outer wall is exposed to high humidity for a long time. The premise is that the material does not absorb water or swell; the extent of the wet area is determined according to the dry-wet zoning plan, and waterproofing should be done first if necessary.
  5. Stain resistance of the booth backrest wall. The booth backrest is where customers lean for long periods, so the wall is easily scuffed. Materials with a dense surface that can be wiped with a neutral cleaner are more suitable; flocked or deeply embossed surfaces are not ideal here.
  6. Straight and smooth joint lines in long corridors. The corridor walls are very long, and once a joint line is skewed, it will be seen repeatedly by moving sightlines. The layout follows a "continuous joints first" approach, aligning joint lines with door frames and column faces.

II. Material comparison: why choose "coarse rammed earth flexible stone"

When comparing wall materials side by side, what really determines the selection is often not "which one looks better," but rather whether the base layer can bear the load, whether the schedule can be compressed, and whether the shape can be achieved.

Comparison item Coarse rammed earth flexible stone Tile / Slab. Natural stone. Traditional wood veneer
Weight per square meterApprox. 4.0–4.4 kg/㎡Noticeably heavier, substrate reinforcement requiredHeaviest; mostly requires dry hangingIncludes thicker base coat
thickness2.5–3 mm6–12 mm15–30 mmIncludes base coat 15 mm or more
Curved surface and columnCan be curved within a certain radius, covering the entire surfaceSmall pieces must be cut and pieced together, with dense jointsRequires waterjet processing; cost and lead time increaseRequires steam heat bending or slitting
Construction methodNo skeleton required, full adhesion after leveling the baseSpecial adhesive, high requirements for joint-gap processMostly dry-hung, requires embedded partsRequires furring strips or a backing board
Moisture-proof and mold-proofDoes not absorb water, does not swellIt does not absorb water itself, but dirt easily collects in the seamsSome stone absorbs waterProne to swelling and mold when damp
ScheduleShort, no wet work or paintingMediumLengthLength
Points to noteNot recommended for ground installationNot good at curved surfacesNot good at special shapesNot good at wet areas

Description: The values in the table above are common ranges for various materials, used to illustrate applicable boundaries and not constituting a ranking of any material. For this project, coarse rammed earth flexible stone was ultimately selected because the rammed earth boards are laid throughout the hall, private rooms and corridors, giving a unified look across areas.

2.0 Why Coarse rammed earth flexible stone

This is a mid-to-high-end hot pot restaurant with private rooms, a wine cabinet and a lounge area; the public area is large and the functions are finely divided. The warm brown tones of the rammed earth panels unify the look of the hall, corridors and private rooms; because there is no wood substrate, it will not swell or delaminate even in the hot, humid environment of a hot pot restaurant over the long term.

2.1 Three questions for selection

Condense the selection into three questions, and the direction can basically be set:

  1. Is the wall curved or column-shaped? Yes → prioritize flexible materials that can bend; No → then compare weight and construction period.
  2. Can the substrate bear the weight of the stone? Cannot (lightweight partition walls, old walls, insulated walls) → prioritize flexible materials; can → natural stone is also an option.
  3. What kind of atmosphere does the space want? Private room lightweight partition walls are directly laid without embedded steel frames for load bearing.

The answers to the three questions for this project: rammed earth panels are laid throughout the hall, private rooms and corridor, creating a unified look across areas; the wine cabinet and shelving are embedded in the wall, with fixing points kept away from panel seams; and the lightweight partition walls of the private rooms are directly applied, with no need for embedded steel frames for load bearing. Therefore, coarse rammed earth flexible stone was selected.

3. Configuration plan

3.1 Material specifications and packaging

Specifications (mm) Thickness (mm) Approx. weight per panel (kg) Wooden crate packaging (pieces/crate) Area of wooden crate after packaging (㎡) Weight after packaging approx. (kg)
600×12002.5–33–3.2300216820
1200×24002.5–312.5–131002881200

Optional colors: white, New South Red, Old South Red (other colors can be customized).

Texture and light perception notes: the layered feel of rammed earth texture comes from surface height differences, and angled lighting creates natural light-dark transitions.

3.2 Allocation by space

Different parts of the same project do not have the same requirements for materials. The table below breaks down the actual space of a mid-to-high-end hot pot restaurant and explains why each part is specified this way.

Space / Location Area share ★ Material usage Why set it this way?
Main viewing surface (the first wall directly facing you when entering)20% or soFull-piece laying, seams kept away from the centerWhere the line of sight rests longest, the overall appearance is most complete
Side walls and passagewaysabout 35%Conventional installation, with joints aligned continuouslyLarge area, with the focus on smooth, continuous seams
Curved wall / partitionabout 15%Full-piece curved wrappingPiecing curved surfaces into small pieces creates dense diagonal seams
Column wrappingabout 8%%Full-piece wrapping on the column surface, with seams kept at the sides and rearThe key is that no seams are visible from the front
Door openings and window casingsabout 10%Use matching termination pieces; do not butt-join on siteCut edges easily expose the panel backing
Form and local areasAbout 12%%Custom-shaped panels according to drawingsOn-site cutting precision for irregular pieces is insufficient

★Description: The proportions in the table above are common distributions for similar spaces and are used to estimate material quantities for each part; actual quantities are subject to on-site measurement and layout drawings.

3.3 Estimation of Quantity and Construction Schedule

The calculation process is given below so it can be reviewed according to your own project's basis.

Project Calculation formula Result
Net installation areaOn-site measurementApprox. 1380㎡
Material preparation area1380 × (1 + 12% waste)Approx. 1546㎡
Number of wooden crates1546 ÷ 216 m²/box, rounded upApprox. 8 boxes
Substrate treatmentLeveling, repair, primer2–3 working days
Layout setting-outSnap lines, align seams, set the starting point1-2 working days
Adhesive mounting5 people in a group, average daily 60-100 ㎡ ★Approx. 19 working days
Finishing and acceptanceEdge trim, cleaning, acceptance1-2 working days
TotalConfigure for 5 people23 working days

3.4 Material List

Auxiliary materials Purpose Description
Special adhesiveMain material for full-surface bonding methodSelect according to product instructions; use weather-resistant type for outdoor or damp areas
Interface agentSubstrate sealingSelect according to substrate material
Edge trim / internal and external corner piecesCorners and closuresSame color family as the main material; prioritize matching accessories rather than on-site cutting
Joint filler materialJoint sealingClose to the main material color number to avoid overly prominent joint lines
DetergentCompletion cleaningNeutral cleaner; strong acids and alkalis prohibited

IV. Construction process and acceptance control points: on-site practice for "coarse rammed earth flexible stone"

4.1 Seven steps

  1. Substrate inspection: Moisture content, flatness, and strength must all pass. Flatness is checked with a 2 m straightedge; sanding and loose layers must be removed down to a solid substrate, and hollow areas must be knocked out and redone.
  2. Substrate treatment: Walls with high moisture content require a sealing primer first; different interface agents are selected for different substrates.
  3. Layout setting-out: Put the layout plan on paper before starting work; mark door and window openings, switches, sockets, and internal/external corner positions; align seam lines across different walls in the same space where possible.
  4. Cutting processing: Cut to layout dimensions; cover cut edges with trim or pressure strips; determine opening positions at the layout stage.
  5. Full bonding installation: The full-surface bonding method is recommended, starting from the main viewing face and progressing to both sides and upward; apply along the arc direction at curved areas.
  6. Finishing treatment: Internal and external corners use matching trim pieces; junctions with door frames, ceilings, and floors are executed according to the node drawings.
  7. Cleaning acceptance: Use a neutral cleaner to remove residual adhesive and fingerprints, and check item by item according to the acceptance checklist.

4.2 Acceptance Control Sheet

Inspection items Control points Criterion
Substrate flatness2 m straightedge inspectionGap not exceeding 3mm ★
Substrate moisture contentSeal damp areas firstNo obvious moisture marks, no water seepage
Joint line alignmentAlign joint lines within the same spaceSmooth and free of steps by visual inspection
Curved-surface installationDirection along the arcNo obvious sharp folds, no edge lifting
External corner closureUse matching termination piecesNo exposed board bottom, consistent color
HollowingSpot-check by tapping each pieceHollowing rate not exceeding 5% ★
Surface cleaningNeutral cleanerNo residual glue, no scratches

The specific allowable deviation values shall be subject to the standards and contract terms of the project location; the table above shows the common industry practice ranges.

4.3 Special methods for arc and column

Curved walls, columns and irregular corners are where flexible materials differ most directly from traditional finishes. There are several points that must be confirmed in advance for the installation method:

Location The method. Items to confirm in advance
Large-radius curved wall (R ≥ 2m)Full-piece curved application, seam following the curve directionArc radius, panel thickness, ambient temperature
Small-radius curved wall (R < 2m)Test the bend first; when there is obvious springback, switch to narrow-strip splicingMust first test bending with a physical mock-up
Cylindrical column claddingFull-piece wrapping, seam left at the side rearColumn diameter and whether there are embedded parts on the column surface
Arches and door openingsContinuous curve, use matching termination piecesDoor opening squareness
Internal and external cornersUse matching termination pieces; do not butt-join on siteWhether the color of finishing pieces is consistent with the main material

4.4 Common problems and avoidance

Phenomenon Reason Workaround
Joint misalignmentUneven substrate, cumulative error block by blockFirst snap lines to control continuous joints, and start installation from the main sightline
Curved-surface edge liftingRadius smaller than the material's usable rangeTest bending before installation to confirm; change to narrower strips if necessary
External corner showing through to the substrateOn-site cutting and butt-joiningUse matching inner and outer corner pieces
The light strip reveals the jointsJoint conflicts with the position of the light stripDetermine the joints together with the light strips during the layout stage
Color difference concentrationMixing different batchesOrder enough at once for the same batch, and mix materials before installation
HollowingBase-layer sanding and insufficient adhesive dosageSubstrate treatment in place, full-adhesion installation

4.5 Construction tools and personnel allocation

Project Configuration Description
Measuring tools2 m straightedge, level, tape measure, chalk lineBase-layer acceptance and chalk-line layout
Cutting toolsUtility knife / board cutting knife, straight rulerOn-site cutting according to layout dimensions
Mixing toolsElectric mixerMix the adhesive according to the specified ratio
Adhesive application toolsNotched trowelFull-surface bonding method: control consistent adhesive layer thickness
Compaction toolPressure roller / rubber malletRemove air bubbles and ensure full adhesion
Cleaning toolsSoft cloth, neutral cleanerCompletion cleaning
StaffingAdhesive mounting, 2–4 people per team ★This project is staffed with 5 people
Daily production capacity per group60–100 square meters per group ★Related to substrate conditions and modeling complexity

★Description: Staffing and daily capacity are common industry ranges, used to estimate the construction period; actual efficiency is affected by substrate conditions, shape complexity, floor height and on-site access conditions.

V. Image display and application description

5.1 Buffet Counter

Buffet table, warm red vertical-grain background wall and wall lamps
Figure 1 · Buffet counter, warm red vertical-grain backdrop wall and wall lamp

5.2 Round Table Booth

Round-table private room, warm red textured wall and decorative painting
Figure 2 · Round-table private room, warm red textured wall and decorative painting

5.3 Wine and Beverage Operation Area

Drinks preparation area, warm red textured background and black wine rack
Figure 3 · Beverage preparation area, warm red textured background and black wine rack

5.4 Rest Area

Rest area, warm red textured wall with green seats
Figure 4 · Lounge area, warm red textured wall and green seating

5.5 Reception Area

Reception area, warm red curved wall, hanging picture, and front desk
Figure 5 · Reception area, warm red curved wall, hanging picture and front desk

5.6 Corridor

Corridor: warm red continuous curved wall with wall lamp
Figure 6 · Corridor, warm red continuous curved wall and wall lamp

5.7 Reception Desk Close-up

Reception desk close-up, warm red background with circular decorative artwork
Figure 7 · Close-up of reception desk, warm red background and circular decorative painting

5.8 Entrance End View

Entrance end feature, warm red curved wall with plant landscape
Figure 8 · Entrance focal point, warm red curved wall and plant landscape

5.9 Booth Area

Booth seating area, warm red wall columns and blue seats
Figure 9 · Booth area, warm red wall columns and blue seating

5.10 lobby dining area

Main hall dining area, warm red textured wall and multiple decorative paintings
Figure 10 · Main hall dining area, warm red textured wall and multiple decorative pictures

5.11 Private room corridor

Private room corridor, warm red textured wall and dark door leaves
Figure 11 · Private room corridor, warm red textured wall and dark door

5.12 Window-side Dining Area

Window-side dining area, warm red wall, window-side bonsai and dining table
Figure 12 · Window-side dining area, warm red wall surface, bonsai by the window and dining table

VI. Communication and confirmation process

The following are several questions confirmed by both parties during material selection and construction, organized in the order of the conversation.

  • Owner: The partition wall between rooms is lightweight steel keel—can it be applied?
  • Our side: Yes. The board is lightweight; after leveling the substrate, simply fully adhere it without embedded steel frames.
  • Design party: A wine cabinet is to be built in the lobby—is it okay to fix the cabinet directly to the wall?
  • Our side: No problem. The expansion fasteners pass through the panel into the substrate, but the cabinet outline must be marked during layout so that fixing points do not fall on joints.
  • Construction party: If the corridor and private rooms use the same option, will there be a color difference?
  • Our side: It is recommended to order enough in a single batch and mix materials once before laying, spreading any possible color differences.
  • Owner: It's over a thousand square meters in total—how long will it take?
  • Our side: Configured for 5 people, about 18 working days, provided the substrate passes acceptance in one go with no rework.

Scope statement: The above is a written summary of the communication content, used to explain the decision-making process; it does not represent a commitment to results, and the contract terms and on-site conditions shall prevail.

Seven, usage effects and daily maintenance

7.1 Perception and light environment

The layered feel of the rammed earth texture comes from the height differences in the surface, and lighting at an angle creates natural light-dark transitions. The same wall looks different under different color temperatures: warmer under warm light and more neutral under cool light, which is also why we recommend sending physical samples first to compare under actual lighting.

7.2 Daily maintenance

Project The method. Note
Daily cleaningWipe with clean water or neutral detergentDo not use strong acids or strong alkalis
Oil stain treatmentNeutral cleaner + soft clothDo not use steel wool
Localized damageIndividual panels can be replacedReplaceable conditions were retained during layout
Damp areasMaintain ventilationDoes not absorb water, does not swell
Outdoor areasRegular washingExecute according to the design scope

7.3 Post-delivery Recheck Sheet

Review items Suggested timing Points of concern
Joints and closures7 days after handoverWhether there is lifting or cracking
Hollowing30 days after handoverSampling and tapping inspection
Color consistency30 days after handoverComparison across different walls and different areas
Cleaning statusDailyWhether there are stubborn stains

7.4 Intersection with Adjacent Materials

Wall materials rarely exist alone; there will always be neighbors such as ceilings, floors, wood veneer, metal parts and glass. How well the junctions are handled directly determines whether the elevation looks "clean" or "fragmented."

Adjacent materials Transition method Note
Ceiling / suspended ceilingPress the edge with a top trim strip, or leave a 3–5 mm revealJoint width must be consistent over the full length
Floor / skirtingSkirting line presses the lower edge of the panelDo not let the bottom edge sit directly on the floor, to avoid dragging wear
Wood finishTransition within the same color family, with the joint left at an internal cornerPlacing the two materials on the same wall requires comparing color differences first
Metal edge trim stripMetal strips press the seam, with the direction parallel to the grain directionColors are mainly matte dark tones to avoid stealing the show
Glass partitionUse a pressure strip for finishing, leaving a caulking gap between the glass and the panelCut edges of the panel need to be covered with trim
Door and window casingsUse matching termination pieces; do not butt-join on siteDoor opening squareness directly affects the finishing result

7.5 Cost Estimation

The cost of a wall consists of three parts: main material + auxiliary materials + labor. The budget estimate basis is as follows (◆budget estimate, not an actual measured bill):

Composition Scope Influencing factors
Main material.Material preparation area approximately 1546 ㎡ ÷ 216 ㎡ per crateColor, thickness, specifications, batch
Auxiliary materialsAdhesive + primer + trim pieces + groutSubstrate conditions, termination complexity
ManualMounting area × labor cost per unit areaForm complexity, floor height, proportion of special shapes

◆Estimate: Specific unit prices vary with pattern, thickness, order quantity, and construction conditions; a wide range is normal. This article does not provide a single quotation to avoid misleading; for project pricing, please provide the area, pattern, and delivery location.

VIII. Common questions (FAQ)

Below are the questions most frequently asked about material selection and construction in this project.

Is coarse rammed earth flexible stone suitable for spaces such as dining areas?

Suitable. The layered feel of the rammed earth texture comes from the surface height variation, and natural light-to-dark transitions appear when light strikes at an angle. This project uses it for the hot pot restaurant's lobby, private rooms, corridor and lounge walls. The rammed earth panels are laid throughout the lobby, private rooms and corridor, giving a consistent look across areas.

Can curved walls and column cladding be done in one continuous piece?

Yes. The material has a certain flexibility and can be bent within a certain radius, so columns, curved walls and irregular corners can achieve full-panel wrapping with continuous seams. The specific usable radius depends on the selected model, thickness and substrate conditions; it is recommended to first test-bend a physical sample at the corresponding curvature to confirm.

How long does the schedule generally take?

This project is approximately 1380 ㎡, staffed with 5 people, and completed in 23 working days (including substrate preparation and finishing). The installation itself accounts for about 19 working days, with the remainder for substrate work, layout marking, and acceptance inspection. The main variable in the schedule is substrate condition—substrate rework will directly eat into the time saved on installation.

Can it be used in damp areas?

Yes. The material itself does not absorb water, and after construction the wall surface is not prone to dampness or mildew, so it can be used in humid environments and underground spaces. For wet areas such as bathrooms, it is recommended to confirm the specific scope in conjunction with the wet/dry zoning plan.

What about fire performance?

The material has flame-retardant properties; the specific combustion performance ratingshall be in accordance with the valid inspection report of the selected model. If the project has specific requirements for fire rating, please specify before placing an order.

How much difference in texture is there compared to natural stone?

Differences are visible up close: natural stone has naturally occurring random variation, while the texture of Coarse Rammed Earth flexible stone is formed by embossing or printing, giving greater consistency within the same product. From a distance the overall look is similar. When placing natural stone and flexible materials on adjacent walls in the same space, it is advisable to make a small sample comparison first.

Can old walls be renovated by direct pasting?

If the original wall surface is firm and has no hollowing, it is possible; old tile surfaces can also be covered directly. But before construction, each surface must be checked for hollowing, and hollowed areas must be knocked out and redone—this step cannot be skipped.

Does the material have test reports? What standard does it follow?

Execution JG/T 540-2017 'Building Flexible Stone-faced Decorative Material' (issued by the Ministry of Housing and Urban-Rural Development). Environmental protection and combustion performance test reports for the corresponding models can be provided with the goods.

How to confirm color and texture?

It is advisable to request physical samples and compare them under the project's actual lighting before deciding the color number. There are differences between screen display and actual materials; in particular, stone-texture materials look different at different angles and color temperatures.

Can a single damaged panel be replaced later?

Yes. During layout, the seam lines and termination positions have already been determined, and a single piece can be pried out from the termination for replacement. It is recommended to reserve 1–2 boxes of same-batch material as spares at delivery.

IX. Project File and Contact Information

Project Content
Project nameHot pot restaurant decoration material recommendation - multi-area application case of rammed earth board flexible stone (Fuling, Chongqing)
LocationFuling District, Chongqing
Main material.Coarse rammed earth flexible stone (warm brown)
Material seriesRammed earth and cement series
Construction areaApprox. 1380㎡
Schedule23 working days
Related sectionsProject Cases · Food & Beverage Spaces
Implementation standardsJG/T 540-2017

Similar projects can be found in the Project Cases column; for material specifications and colors see Rammed earth and cement series.


Legend and specification notes

  • ★Project experience = Industry common practice and experience range, not a reference for national standard data.
  • ◆Estimate = Estimated value calculated based on the scale,not an actual measured bill; actual conditions are subject to the contract agreement and site conditions.
  • Material parameters are taken from the corresponding product file; combustion performance, environmental grade, etc. are subject to the valid test report for the selected model.
  • Area, schedule, and quantity are estimates based on industry-scale figures; the calculation process is provided and can be reviewed against your own project's basis.

Find the appropriate wall expression for your project.

Provide the type of space, wall area, and design intention. Communicate about materials, samples, and quotations.

Consulting project material selection ↗
Contact phone number Product Catalog Free Sample
WeChat ID copied