Eyewear store 120㎡ travertine (printed travertine) wall construction case

The eyewear store project is located in Fuzhou, Fujian Province, and the main wall material is travertine flexible stone (printed travertine), used for the eyewear store storefront and in-store display background wall. The construction area is about 120 ㎡, completed by 3 people in 4 working days. This article explains the material selection basis, quantity and schedule estimation, construction control points, application images and common questions at once.

Published time:

Introduction

The eyewear store project is located in Fuzhou, Fujian Province, and the main wall material is travertine Flexible Stone (Printed travertine), used for the storefront and in-store display feature wall of an eyewear store, with a construction area of approximately 120 ㎡, completed by 3 workers in 4 working days. This article explains in one go the basis for material selection, quantity and schedule estimates, construction control points, application photos and frequently asked questions.

  • Project: Eyewear store · Eyewear store storefront and in-store display background wall
  • Location: Fuzhou City, Fujian Province
  • Main material: Travertine flexible stone (printed travertine)
  • Construction area: Approx. 120 ㎡
  • Schedule: 4 working days / 3 people
  • Implementation standards: JG/T 540-2017

Project file

Project Content
Space typeRetail storefront
Business typeEyewear store
CityFuzhou City, Fujian Province
ScaleStorefront + in-store background wall
Construction locationEyewear store storefront and in-store display background wall
Main material.Travertine flexible stone (printed travertine)
Construction areaApprox. 120㎡
Construction period4 working days
Number of construction workers3 people
Implementation standardsJG/T 540-2017"Flexible Stone-like Facing Materials for Buildings"

1. Customer industry usage scenario: the real wall requirements of an eyewear store

  1. The storefront is the only advertising space for a small shop. The foot traffic of a small street-front shop depends entirely on the storefront; the recognizability of the material and its coordination with lighting determine the entry rate.
  2. Semi-outdoor interfaces must be weather-resistant The facade wall is directly exposed to wind and rain, so weather-resistant adhesive must be used and waterproof edge trim must be done.
  3. Fixing of signage, light boxes and canopies Fasteners pass through the panel into the substrate, and the sign outline must be marked during the layout stage.
  4. Nighttime viewing takes priority The peak of street-front stores is after evening, and storefront evaluation mainly occurs under nighttime lighting.
  5. Small scale, dense edge finishing The door frame, light box, and canopy of a small shopfront are crowded together, so the amount of closure work relative to area is far higher than in large-area projects.
  6. Renovation during business hours must control the construction period Closing a small shop means lost revenue, so methods that require no framing and no wet work can significantly shorten the schedule.

II. Material comparison: why choose "travertine flexible stone"

When comparing wall materials side by side, what really determines the selection is often not "which one looks better," but rather whether the base layer can bear the load, whether the schedule can be compressed, and whether the shape can be achieved.

Comparison item Travertine flexible stone Tile / Slab. Natural stone. Traditional wood veneer
Weight per square meterApprox. 3.5–3.9 kg/㎡Noticeably heavier, substrate reinforcement requiredHeaviest; mostly requires dry hangingIncludes thicker base coat
thickness2.3-2.8 mm6–12 mm15–30 mmIncludes base coat 15 mm or more
Curved surface and columnCan be curved within a certain radius, covering the entire surfaceSmall pieces must be cut and pieced together, with dense jointsRequires waterjet processing; cost and lead time increaseRequires steam heat bending or slitting
Construction methodNo skeleton required, full adhesion after leveling the baseSpecial adhesive, high requirements for joint-gap processMostly dry-hung, requires embedded partsRequires furring strips or a backing board
Moisture-proof and mold-proofDoes not absorb water, does not swellIt does not absorb water itself, but dirt easily collects in the seamsSome stone absorbs waterProne to swelling and mold when damp
ScheduleShort, no wet work or paintingMediumLengthLength
Points to noteNot recommended for ground installationNot good at curved surfacesNot good at special shapesNot good at wet areas

Description: The values in the table above are common ranges for various materials, used to illustrate applicable boundaries and not constituting a ranking of any material. For this project, travertine flexible stone was ultimately selected because the light-colored pore texture of the travertine forms a material contrast with the metal display racks.

2.0 Why Travertine Flexible Stone

The pore texture has actual relief, and shadow layers appear under angled light. The light-colored pore texture of travertine forms a material contrast with metal display racks.

2.1 Three questions for selection

  1. Is the wall curved or column-shaped? Yes → prioritize flexible materials that can bend; No → then compare weight and construction period.
  2. Can the substrate bear the weight of the stone? Cannot (lightweight partition walls, old walls, insulated walls) → prioritize flexible materials; can → natural stone is also an option.
  3. What kind of atmosphere does the space want? A light-colored base does not interfere with the visual focus of merchandise display.

Answers to the three questions for this project: the light-colored porous texture of travertine forms a material contrast with the metal display racks; the storefront is constructed to weather-resistant specifications, with waterproofing at the edges; the light background does not interfere with the visual focus of the merchandise display. Therefore, travertine flexible stone was chosen.

3. Configuration plan

3.1 Material specifications and packaging

Specifications (mm) Thickness (mm) Approx. weight per panel (kg) Wooden crate packaging (pieces/crate) Area of wooden crate after packaging (㎡) Weight after packaging approx. (kg)
600×12002.3-2.82.5-2.8330237.6900
1200×24002.3-2.810.5-111002881170
1200×30003.5-417-18802881390

Optional colors: gray, white (other colors can be customized).

Texture and light perception notes: The travertine texture has actual relief, creating layered shadows under oblique lighting.

3.2 Allocation by space

Different parts of the same project do not have the same requirements for materials. The table below breaks down the actual space of an eyewear store and explains why each part is specified this way.

Space / Location Area share ★ Material usage Why set it this way?
Main viewing surface (the first wall directly facing you when entering)20% or soFull-piece laying, seams kept away from the centerWhere the line of sight rests longest, the overall appearance is most complete
Side walls and passagewaysabout 35%Conventional installation, with joints aligned continuouslyLarge area, with the focus on smooth, continuous seams
Curved wall / partitionabout 15%Full-piece curved wrappingPiecing curved surfaces into small pieces creates dense diagonal seams
Column wrappingabout 8%%Full-piece wrapping on the column surface, with seams kept at the sides and rearThe key is that no seams are visible from the front
Door openings and window casingsabout 10%Use matching termination pieces; do not butt-join on siteCut edges easily expose the panel backing
Form and local areasAbout 12%%Custom-shaped panels according to drawingsOn-site cutting precision for irregular pieces is insufficient

★Description: The proportions in the table above are common distributions for similar spaces and are used to estimate material quantities for each part; actual quantities are subject to on-site measurement and layout drawings.

3.3 Estimation of Quantity and Construction Schedule

The calculation process is given below so it can be reviewed according to your own project's basis.

Project Calculation formula Result
Net installation areaOn-site measurementApprox. 120㎡
Material preparation area120 × (1 + 12% loss)Approx. 134㎡
Number of wooden crates134 ÷ 237.6, round upApprox. 1 box
Substrate treatmentLeveling, repair, primer2–3 working days
Layout setting-outSnap lines, align seams, set the starting point1-2 working days
Adhesive mounting3 people per group, average 60-100㎡ per day ★Approx. 1 working day
Finishing and acceptanceEdge trim, cleaning, acceptance1-2 working days
TotalConfigure for 3 people4 working days

3.4 Material List

Auxiliary materials Purpose Description
Special adhesiveMain material for full-surface bonding methodSelect according to product instructions; use weather-resistant type for outdoor or damp areas
Interface agentSubstrate sealingSelect according to substrate material
Edge trim / internal and external corner piecesCorners and closuresSame color family as the main material; prioritize matching accessories rather than on-site cutting
Joint filler materialJoint sealingClose to the main material color number to avoid overly prominent joint lines
DetergentCompletion cleaningNeutral cleaner; strong acids and alkalis prohibited

IV. Construction process and acceptance control points: on-site practice for "travertine flexible stone"

4.1 Seven steps

  1. Substrate inspection: Moisture content, flatness, and strength must all pass. Flatness is checked with a 2 m straightedge; sanding and loose layers must be removed down to a solid substrate, and hollow areas must be knocked out and redone.
  2. Substrate treatment: Walls with high moisture content require a sealing primer first; different interface agents are selected for different substrates.
  3. Layout setting-out: Put the layout plan on paper before starting work; mark door and window openings, switches, sockets, and internal/external corner positions; align seam lines across different walls in the same space where possible.
  4. Cutting processing: Cut to layout dimensions; cover cut edges with trim or pressure strips; determine opening positions at the layout stage.
  5. Full bonding installation: The full-surface bonding method is recommended, starting from the main viewing face and progressing to both sides and upward; apply along the arc direction at curved areas.
  6. Finishing treatment: Internal and external corners use matching trim pieces; junctions with door frames, ceilings, and floors are executed according to the node drawings.
  7. Cleaning acceptance: Use a neutral cleaner to remove residual adhesive and fingerprints, and check item by item according to the acceptance checklist.

4.2 Acceptance Control Sheet

Inspection items Control points Criterion
Substrate flatness2 m straightedge inspectionGap not exceeding 3mm ★
Substrate moisture contentSeal damp areas firstNo obvious moisture marks, no water seepage
Joint line alignmentAlign joint lines within the same spaceSmooth and free of steps by visual inspection
Curved-surface installationDirection along the arcNo obvious sharp folds, no edge lifting
External corner closureUse matching termination piecesNo exposed board bottom, consistent color
HollowingSpot-check by tapping each pieceHollowing rate not exceeding 5% ★
Surface cleaningNeutral cleanerNo residual glue, no scratches

The specific allowable deviation values shall be subject to the standards and contract terms of the project location; the table above shows the common industry practice ranges.

4.3 Special methods for arc and column

Location The method. Items to confirm in advance
Large-radius curved wall (R ≥ 2m)Full-piece curved application, seam following the curve directionArc radius, panel thickness, ambient temperature
Small-radius curved wall (R < 2m)Test the bend first; when there is obvious springback, switch to narrow-strip splicingMust first test bending with a physical mock-up
Cylindrical column claddingFull-piece wrapping, seam left at the side rearColumn diameter and whether there are embedded parts on the column surface
Arches and door openingsContinuous curve, use matching termination piecesDoor opening squareness
Internal and external cornersUse matching termination pieces; do not butt-join on siteWhether the color of finishing pieces is consistent with the main material

4.4 Common problems and avoidance

Phenomenon Reason Workaround
Joint misalignmentUneven substrate, cumulative error block by blockFirst snap lines to control continuous joints, and start installation from the main sightline
Curved-surface edge liftingRadius smaller than the material's usable rangeTest bending before installation to confirm; change to narrower strips if necessary
External corner showing through to the substrateOn-site cutting and butt-joiningUse matching inner and outer corner pieces
The light strip reveals the jointsJoint conflicts with the position of the light stripDetermine the joints together with the light strips during the layout stage
Color difference concentrationMixing different batchesOrder enough at once for the same batch, and mix materials before installation
HollowingBase-layer sanding and insufficient adhesive dosageSubstrate treatment in place, full-adhesion installation

4.5 Construction tools and personnel allocation

Project Configuration Description
Measuring tools2 m straightedge, level, tape measure, chalk lineBase-layer acceptance and chalk-line layout
Cutting toolsUtility knife / board cutting knife, straight rulerOn-site cutting according to layout dimensions
Mixing toolsElectric mixerMix the adhesive according to the specified ratio
Adhesive application toolsNotched trowelFull-surface bonding method: control consistent adhesive layer thickness
Compaction toolPressure roller / rubber malletRemove air bubbles and ensure full adhesion
Cleaning toolsSoft cloth, neutral cleanerCompletion cleaning
StaffingAdhesive mounting, 2–4 people per team ★This project is staffed with 3 people
Daily production capacity per group60–100 square meters per group ★Related to substrate conditions and modeling complexity

V. Image display and application description

5.1 Store Identification Wall

Store sign wall, beige horizontal texture finish and illuminated sign
Figure 1 · Store signage wall, beige horizontal-texture finish and illuminated sign

5.2 Facade corner

Facade corner, close-up of beige horizontal stone-grain finish
Figure 2 · Facade corner, beige horizontal stone-textured finish close-up

5.3 Fire facility panel

Fire facility panel, beige textured finish with text signage
Figure 3 · Fire facility panel, beige textured finish with text signage

5.4 Front of Eyewear Store

Eyewear store frontage, beige horizontal-grain storefront and glass door
Figure 4 · Eyewear store facade, beige horizontal-grain storefront header and glass door

5.5 Store Side

Side of the shop door, beige textured finish and glass door frame
Figure 5 · Side of the store entrance, beige textured finish and glass door frame

5.6 Arc column close-up

Close-up of curved column, beige horizontal texture and lighting
Figure 6 · Close-up of the curved column, beige horizontal texture and lighting

5.7 Column surface close-up

Close-up of the column surface, fine pores and horizontal lines on the beige finish
Figure 7 · Close-up of column surface, fine pores and horizontal grain on the beige finish

5.8 Storefront facade

Shop door facade, beige horizontal texture and dark frame
Figure 8 · Storefront facade, beige horizontal texture and dark frame

VI. Communication and confirmation process

The following are several questions confirmed by both parties during material selection and construction, organized in the order of the conversation.

  • Shop owner: Eyewear needs lighting, and the wall surface must not reflect light.
  • Our side: Travertine has a matte surface, so spotlighting does not create light spots, making display lighting easier to control.
  • Construction party: The light box and rain canopy of the small entrance are very close together.
  • Our side: Mark their outlines all at once during layout, and keep fixing components uniformly clear of board joints.

Scope statement: The above is a written summary of the communication content, used to explain the decision-making process; it does not represent a commitment to results, and the contract terms and on-site conditions shall prevail.

Seven, usage effects and daily maintenance

7.1 Perception and light environment

The travertine texture has actual relief, and shadow layers appear under angled light. The same wall looks different under different color temperatures: warmer under warm light and more neutral under cool light, which is also why it is recommended to first compare physical samples under actual lighting.

7.2 Daily maintenance

Project The method. Note
Daily cleaningWipe with clean water or neutral detergentDo not use strong acids or strong alkalis
Oil stain treatmentNeutral cleaner + soft clothDo not use steel wool
Localized damageIndividual panels can be replacedReplaceable conditions were retained during layout
Damp areasMaintain ventilationDoes not absorb water, does not swell
Outdoor areasRegular washingExecute according to the design scope

7.3 Post-delivery Recheck Sheet

Review items Suggested timing Points of concern
Joints and closures7 days after handoverWhether there is lifting or cracking
Hollowing30 days after handoverSampling and tapping inspection
Color consistency30 days after handoverComparison across different walls and different areas
Cleaning statusDailyWhether there are stubborn stains

7.4 Intersection with Adjacent Materials

Adjacent materials Transition method Note
Ceiling / suspended ceilingPress the edge with a top trim strip, or leave a 3–5 mm revealJoint width must be consistent over the full length
Floor / skirtingSkirting line presses the lower edge of the panelDo not let the bottom edge sit directly on the floor, to avoid dragging wear
Wood finishTransition within the same color family, with the joint left at an internal cornerPlacing the two materials on the same wall requires comparing color differences first
Metal edge trim stripMetal strips press the seam, with the direction parallel to the grain directionColors are mainly matte dark tones to avoid stealing the show
Glass partitionUse a pressure strip for finishing, leaving a caulking gap between the glass and the panelCut edges of the panel need to be covered with trim
Door and window casingsUse matching termination pieces; do not butt-join on siteDoor opening squareness directly affects the finishing result

7.5 Cost Estimation

Composition Scope Influencing factors
Main material.Material preparation area approximately 134 ㎡Color, thickness, specifications, batch
Auxiliary materialsAdhesive + primer + trim pieces + groutSubstrate conditions, termination complexity
ManualMounting area × labor cost per unit areaForm complexity, floor height, proportion of special shapes

◆Estimate: Specific unit prices vary with pattern, thickness, order quantity, and construction conditions; a wide range is normal. This article does not provide a single quotation to avoid misleading; for project pricing, please provide the area, pattern, and delivery location.

VIII. Common questions (FAQ)

Is travertine flexible stone suitable for spaces like retail storefronts?

Suitable. The porous texture has actual relief, and shadow layers appear under angled light. This project uses it for the eyewear store's storefront and in-store display backdrop wall. The light-colored porous texture of the travertine forms a material contrast with the metal display racks.

Can curved walls and column cladding be done in one continuous piece?

Yes. The material has a certain flexibility and can be bent within a certain radius, so columns, curved walls and irregular corners can achieve full-panel wrapping with continuous seams. The specific usable radius depends on the selected model, thickness and substrate conditions; it is recommended to first test-bend a physical sample at the corresponding curvature to confirm.

How long does the schedule generally take?

This project is about 120 ㎡, with 3 workers, completed in 4 working days (including substrate treatment and edge finishing). The installation itself accounts for about 1 working day, with the rest for substrate, layout, and acceptance. The main variable in the schedule is the substrate condition—substrate rework will directly eat up the time saved by installation.

Can it be used in damp areas?

Yes. The material itself does not absorb water, and after construction the wall surface is not prone to dampness or mildew, so it can be used in humid environments and underground spaces. For wet areas such as bathrooms, it is recommended to confirm the specific scope in conjunction with the wet/dry zoning plan.

What about fire performance?

The material has flame-retardant properties; the specific combustion performance ratingshall be in accordance with the valid inspection report of the selected model. If the project has specific requirements for fire rating, please specify before placing an order.

How much difference in texture is there compared to natural stone?

Differences are visible up close: natural stone has naturally occurring random variation, while the texture of travertine flexible stone is formed by embossing or printing, giving greater consistency within the same product. From a distance the overall look is similar. When placing natural stone and flexible materials on adjacent walls in the same space, it is advisable to make a small sample comparison first.

Can old walls be renovated by direct pasting?

If the original wall surface is firm and has no hollowing, it is possible; old tile surfaces can also be covered directly. But before construction, each surface must be checked for hollowing, and hollowed areas must be knocked out and redone—this step cannot be skipped.

Does the material have test reports? What standard does it follow?

Execution JG/T 540-2017 'Building Flexible Stone-faced Decorative Material' (issued by the Ministry of Housing and Urban-Rural Development). Environmental protection and combustion performance test reports for the corresponding models can be provided with the goods.

How to confirm color and texture?

It is advisable to request physical samples and compare them under the project's actual lighting before deciding the color number. There are differences between screen display and actual materials; in particular, stone-texture materials look different at different angles and color temperatures.

Can a single damaged panel be replaced later?

Yes. During layout, the seam lines and termination positions have already been determined, and a single piece can be pried out from the termination for replacement. It is recommended to reserve 1–2 boxes of same-batch material as spares at delivery.

IX. Project File and Contact Information

Project Content
LocationFuzhou City, Fujian Province
Main material.Travertine flexible stone (printed travertine)
Material seriesTravertine series
Construction areaApprox. 120㎡
Schedule4 working days
Related sectionsProject Cases · Retail storefront
Implementation standardsJG/T 540-2017

Similar projects can be found in the Project Cases column; for material specifications and colors see Travertine series.


Legend and specification notes

  • ★Project experience = Industry common practice and experience range, not a reference for national standard data.
  • ◆Estimate = Estimated value calculated based on the scale,not an actual measured bill; actual conditions are subject to the contract agreement and site conditions.
  • Material parameters are taken from the corresponding product file; combustion performance, environmental grade, etc. are subject to the valid test report for the selected model.
  • Area, schedule, and quantity are estimates based on industry-scale figures; the calculation process is provided and can be reviewed against your own project's basis.

Find the appropriate wall expression for your project.

Provide the type of space, wall area, and design intention. Communicate about materials, samples, and quotations.

Consulting project material selection ↗
Contact phone number Product Catalog Free Sample
WeChat ID copied