Korean BBQ restaurant 780㎡ woven linen flexible stone (warm brown) wall construction case

The Korean BBQ restaurant project is located in Duyun City, Guizhou Province, and the main wall material selected is woven linen flexible stone (warm brown), used for the Korean BBQ restaurant cashier counter background, self-service station and hall walls. The construction area is about 780 ㎡, completed by 4 people in 14 working days.

Published time:

Introduction

The Korean BBQ restaurant project is located in Duyun City, Guizhou Province, and the main wall material selected is Linen weave flexible stone Flexible Stone (warm brown), used for the cashier counter background, self-service counter, and main hall walls of a barbecue restaurant, with a construction area of about 780 ㎡, completed by 4 people in 14 working days. This article explains the material selection basis, quantity and schedule estimation, construction control points, application photos, and common questions all at once.

  • Project: Korean BBQ restaurant · Korean BBQ restaurant cashier counter backdrop, self-service counter, and hall wall surfaces
  • Location: Duyun City, Guizhou Province
  • Main material: Hemp weave Soft stone Flexible stone (warm brown)
  • Construction area: approx. 780 ㎡
  • Schedule: 14 working days / 4 people
  • Implementation standards: JG/T 540-2017

Project file

Project Content
Space typeDining cashier counter
Business typeKorean BBQ restaurant
CityDuyun City, Guizhou Province
ScaleMain hall, 24 tables + buffet station
Construction locationKorean BBQ restaurant cashier counter background, self-service station and hall walls
Main material.Linen weave flexible stone (warm brown)
Construction areaApprox. 780 ㎡
Construction period14 working days
Number of construction workers4 people
Implementation standardsJG/T 540-2017"Flexible Stone-like Facing Materials for Buildings"

1. Customer industry usage scenario: the real wall requirements of a Korean BBQ restaurant

  1. The cashier counter is where customers linger and focus their gaze Ordering, checkout and waiting for a table all happen in this small area. The wall will be viewed up close and will also be repeatedly touched by hands and plates.
  2. Scrub resistance of high-frequency contact surfaces The 90–140 cm zone above the countertop is the most frequently contacted height band; the layout should avoid positions subject to frequent rubbing, or use cleanable edge trims as transitions.
  3. The feature wall should coordinate with the brand identity Cashier counter backgrounds usually hold brand light boxes or dish displays. Wall reflections compete with signage for attention; low-reflectance materials make signage easier to read.
  4. The junction between countertop and wall must be detailed according to the node. Countertops are often made as a whole with the wall in the same material. Two hard materials must not butt directly; leave a process joint or use a trim piece as a transition.
  5. Oil mist and steam in dining environments Cashier counters are often close to the pass or open kitchen and sit in oil mist long-term. A dense surface that does not absorb water is a basic requirement.
  6. Performance under nighttime lighting Cashier counter lighting is usually accent lighting; the material's performance in this location must be confirmed under actual light positions, not in the showroom.

II. Material comparison: why choose "hemp-woven soft stone flexible stone"

When comparing wall materials side by side, what really determines the selection is often not "which one looks better," but rather whether the base layer can bear the load, whether the schedule can be compressed, and whether the shape can be achieved.

Comparison item Linen weave flexible stone Tile / Slab. Natural stone. Traditional wood veneer
Weight per square meterApprox. 5.0–5.6 kg/㎡Noticeably heavier, substrate reinforcement requiredHeaviest; mostly requires dry hangingIncludes thicker base coat
thickness3.5-5.5 mm6–12 mm15–30 mmIncludes base coat 15 mm or more
Curved surface and columnCan be curved within a certain radius, covering the entire surfaceSmall pieces must be cut and pieced together, with dense jointsRequires waterjet processing; cost and lead time increaseRequires steam heat bending or slitting
Construction methodNo skeleton required, full adhesion after leveling the baseSpecial adhesive, high requirements for joint-gap processMostly dry-hung, requires embedded partsRequires furring strips or a backing board
Moisture-proof and mold-proofDoes not absorb water, does not swellIt does not absorb water itself, but dirt easily collects in the seamsSome stone absorbs waterProne to swelling and mold when damp
ScheduleShort, no wet work or paintingMediumLengthLength
Points to noteNot recommended for ground installationNot good at curved surfacesNot good at special shapesNot good at wet areas

Description: The values in the table above are common ranges for various materials, used to illustrate applicable boundaries and not constituting a ranking of any material. For this project, woven hemp soft stone flexible stone was ultimately selected because the warm brown woven hemp soft stone presents a rich, mellow overall base tone under the warm light of the oven.

2.0 Why choose Linen weave flexible stone

The woven texture has a handmade feel up close and reads as a whole soft base color from a distance. The warm brown woven linen flexible stone presents a rich, full base color under the warm light of the oven.

2.1 Three questions for selection

  1. Is the wall curved or column-shaped? Yes → prioritize flexible materials that can bend; No → then compare weight and construction period.
  2. Can the substrate bear the weight of the stone? Cannot (lightweight partition walls, old walls, insulated walls) → prioritize flexible materials; can → natural stone is also an option.
  3. What kind of atmosphere does the space want? The woven texture is scrub-resistant, suitable for high-frequency cleaning environments in food and beverage venues.

The answers to the three questions for this project: the warm brown woven-texture soft stone presents a rich overall base color under the warm light of the oven; the cashier counter background matches the hall, creating a unified look across areas; and the woven texture is scrub-resistant, suitable for the high-frequency cleaning environment of food service. Therefore, woven-texture soft stone flexible stone was selected.

3. Configuration plan

3.1 Material specifications and packaging

Specifications (mm) Thickness (mm) Approx. weight per panel (kg) Wooden crate packaging (pieces/crate) Area of wooden crate after packaging (㎡) Weight after packaging approx. (kg)
600×12003.5-5.54220158.4920
1200×30003.5-5.520602161355

Optional colors: New South Red, Old South Red, Beige (other colors can be customized).

Texture and light perception notes: The woven texture has a handmade feel up close and reads as a whole soft base color from a distance.

3.2 Allocation by space

Different parts of the same project do not have the same requirements for materials. The table below breaks down the actual space of a barbecue restaurant and explains why each part is specified this way.

Space / Location Area share ★ Material usage Why set it this way?
Main viewing surface (the first wall directly facing you when entering)20% or soFull-piece laying, seams kept away from the centerWhere the line of sight rests longest, the overall appearance is most complete
Side walls and passagewaysabout 35%Conventional installation, with joints aligned continuouslyLarge area, with the focus on smooth, continuous seams
Curved wall / partitionabout 15%Full-piece curved wrappingPiecing curved surfaces into small pieces creates dense diagonal seams
Column wrappingabout 8%%Full-piece wrapping on the column surface, with seams kept at the sides and rearThe key is that no seams are visible from the front
Door openings and window casingsabout 10%Use matching termination pieces; do not butt-join on siteCut edges easily expose the panel backing
Form and local areasAbout 12%%Custom-shaped panels according to drawingsOn-site cutting precision for irregular pieces is insufficient

★Description: The proportions in the table above are common distributions for similar spaces and are used to estimate material quantities for each part; actual quantities are subject to on-site measurement and layout drawings.

3.3 Estimation of Quantity and Construction Schedule

The calculation process is given below so it can be reviewed according to your own project's basis.

Project Calculation formula Result
Net installation areaOn-site measurementApprox. 780 ㎡
Material preparation area780 × (1 + 12% loss)Approx. 874 ㎡
Number of wooden crates874 ÷ 158.4, rounded upApprox. 6 boxes
Substrate treatmentLeveling, repair, primer2–3 working days
Layout setting-outSnap lines, align seams, set the starting point1-2 working days
Adhesive mounting4 people in a group, average daily 60–100 m² ★Approx. 11 business days
Finishing and acceptanceEdge trim, cleaning, acceptance1-2 working days
TotalConfigure for 4 people14 working days

3.4 Material List

Auxiliary materials Purpose Description
Special adhesiveMain material for full-surface bonding methodSelect according to product instructions; use weather-resistant type for outdoor or damp areas
Interface agentSubstrate sealingSelect according to substrate material
Edge trim / internal and external corner piecesCorners and closuresSame color family as the main material; prioritize matching accessories rather than on-site cutting
Joint filler materialJoint sealingClose to the main material color number to avoid overly prominent joint lines
DetergentCompletion cleaningNeutral cleaner; strong acids and alkalis prohibited

IV. Construction process and acceptance control points: on-site practice for "hemp-woven soft stone flexible stone"

4.1 Seven steps

  1. Substrate inspection: Moisture content, flatness, and strength must all pass. Flatness is checked with a 2 m straightedge; sanding and loose layers must be removed down to a solid substrate, and hollow areas must be knocked out and redone.
  2. Substrate treatment: Walls with high moisture content require a sealing primer first; different interface agents are selected for different substrates.
  3. Layout setting-out: Put the layout plan on paper before starting work; mark door and window openings, switches, sockets, and internal/external corner positions; align seam lines across different walls in the same space where possible.
  4. Cutting processing: Cut to layout dimensions; cover cut edges with trim or pressure strips; determine opening positions at the layout stage.
  5. Full bonding installation: The full-surface bonding method is recommended, starting from the main viewing face and progressing to both sides and upward; apply along the arc direction at curved areas.
  6. Finishing treatment: Internal and external corners use matching trim pieces; junctions with door frames, ceilings, and floors are executed according to the node drawings.
  7. Cleaning acceptance: Use a neutral cleaner to remove residual adhesive and fingerprints, and check item by item according to the acceptance checklist.

4.2 Acceptance Control Sheet

Inspection items Control points Criterion
Substrate flatness2 m straightedge inspectionGap not exceeding 3mm ★
Substrate moisture contentSeal damp areas firstNo obvious moisture marks, no water seepage
Joint line alignmentAlign joint lines within the same spaceSmooth and free of steps by visual inspection
Curved-surface installationDirection along the arcNo obvious sharp folds, no edge lifting
External corner closureUse matching termination piecesNo exposed board bottom, consistent color
HollowingSpot-check by tapping each pieceHollowing rate not exceeding 5% ★
Surface cleaningNeutral cleanerNo residual glue, no scratches

The specific allowable deviation values shall be subject to the standards and contract terms of the project location; the table above shows the common industry practice ranges.

4.3 Special methods for arc and column

Location The method. Items to confirm in advance
Large-radius curved wall (R ≥ 2m)Full-piece curved application, seam following the curve directionArc radius, panel thickness, ambient temperature
Small-radius curved wall (R < 2m)Test the bend first; when there is obvious springback, switch to narrow-strip splicingMust first test bending with a physical mock-up
Cylindrical column claddingFull-piece wrapping, seam left at the side rearColumn diameter and whether there are embedded parts on the column surface
Arches and door openingsContinuous curve, use matching termination piecesDoor opening squareness
Internal and external cornersUse matching termination pieces; do not butt-join on siteWhether the color of finishing pieces is consistent with the main material

4.4 Common problems and avoidance

Phenomenon Reason Workaround
Joint misalignmentUneven substrate, cumulative error block by blockFirst snap lines to control continuous joints, and start installation from the main sightline
Curved-surface edge liftingRadius smaller than the material's usable rangeTest bending before installation to confirm; change to narrower strips if necessary
External corner showing through to the substrateOn-site cutting and butt-joiningUse matching inner and outer corner pieces
The light strip reveals the jointsJoint conflicts with the position of the light stripDetermine the joints together with the light strips during the layout stage
Color difference concentrationMixing different batchesOrder enough at once for the same batch, and mix materials before installation
HollowingBase-layer sanding and insufficient adhesive dosageSubstrate treatment in place, full-adhesion installation

4.5 Construction tools and personnel allocation

Project Configuration Description
Measuring tools2 m straightedge, level, tape measure, chalk lineBase-layer acceptance and chalk-line layout
Cutting toolsUtility knife / board cutting knife, straight rulerOn-site cutting according to layout dimensions
Mixing toolsElectric mixerMix the adhesive according to the specified ratio
Adhesive application toolsNotched trowelFull-surface bonding method: control consistent adhesive layer thickness
Compaction toolPressure roller / rubber malletRemove air bubbles and ensure full adhesion
Cleaning toolsSoft cloth, neutral cleanerCompletion cleaning
StaffingAdhesive mounting, 2–4 people per team ★This project is staffed with 4 people
Daily production capacity per group60–100 square meters per group ★Related to substrate conditions and modeling complexity

V. Image display and application description

5.1 Cashier Area

Cashier area, brown woven-texture feature wall with tabletop display
Figure 1 · Cashier area, brown woven-texture feature wall and tabletop display

5.2 Brown Texture Wall, Wall Lamps and Paintings

Brown textured wall, wall lamp and hanging picture
Figure 2 · Brown textured wall, wall lamp and hanging painting

5.3 Indoor Side Counter

Indoor side counter, brown textured wall with lantern-style wall lamp
Fig. 3 · Indoor side counter, brown textured wall and lantern-style wall lamp

5.4 Entrance Corner

Entrance corner, knotted decorative partition with brown textured wall
Figure 4 · Entrance corner, knotted decorative partition and brown textured wall

5.5 Beverage display stand

Drinks display counter, brown textured background with bottles and jars
Figure 5 · Beverage display counter, brown textured backdrop and bottles and jars

5.6 Wall next to barbecue

Wall beside the grill station, coarse and fine woven texture with wall lamp
Figure 6 · Wall beside the grill station, coarse and fine woven textures and wall lamp

5.7 condiment display area

Condiment display area, brown textured wall and wood-colored side counter
Figure 7 · Condiment display area, brown textured wall and wood-colored side table

VI. Communication and confirmation process

The following are several questions confirmed by both parties during material selection and construction, organized in the order of the conversation.

  • Owner: Korean BBQ restaurants have heavy grease fumes; are the walls easy to maintain?
  • Our side: The surface is dense; neutral cleaner plus a soft cloth is enough. Do not use steel wool; the woven texture will be worn flat.
  • Design party: I want to put a lightbox on the cashier counter background.
  • Our side: Yes. Mark the light box outline during layout; fasteners should pass through the board into the substrate and not press on the seams.

Scope statement: The above is a written summary of the communication content, used to explain the decision-making process; it does not represent a commitment to results, and the contract terms and on-site conditions shall prevail.

Seven, usage effects and daily maintenance

7.1 Perception and light environment

The woven texture has a handmade feel up close and reads as a whole soft base color from a distance. The same wall looks different under different color temperatures: warmer under warm light and more neutral under cool light, which is also why we recommend comparing physical samples under actual lighting first.

7.2 Daily maintenance

Project The method. Note
Daily cleaningWipe with clean water or neutral detergentDo not use strong acids or strong alkalis
Oil stain treatmentNeutral cleaner + soft clothDo not use steel wool
Localized damageIndividual panels can be replacedReplaceable conditions were retained during layout
Damp areasMaintain ventilationDoes not absorb water, does not swell
Outdoor areasRegular washingExecute according to the design scope

7.3 Post-delivery Recheck Sheet

Review items Suggested timing Points of concern
Joints and closures7 days after handoverWhether there is lifting or cracking
Hollowing30 days after handoverSampling and tapping inspection
Color consistency30 days after handoverComparison across different walls and different areas
Cleaning statusDailyWhether there are stubborn stains

7.4 Intersection with Adjacent Materials

Adjacent materials Transition method Note
Ceiling / suspended ceilingPress the edge with a top trim strip, or leave a 3–5 mm revealJoint width must be consistent over the full length
Floor / skirtingSkirting line presses the lower edge of the panelDo not let the bottom edge sit directly on the floor, to avoid dragging wear
Wood finishTransition within the same color family, with the joint left at an internal cornerPlacing the two materials on the same wall requires comparing color differences first
Metal edge trim stripMetal strips press the seam, with the direction parallel to the grain directionColors are mainly matte dark tones to avoid stealing the show
Glass partitionUse a pressure strip for finishing, leaving a caulking gap between the glass and the panelCut edges of the panel need to be covered with trim
Door and window casingsUse matching termination pieces; do not butt-join on siteDoor opening squareness directly affects the finishing result

7.5 Cost Estimation

Composition Scope Influencing factors
Main material.Preparation area approx. 874 ㎡Color, thickness, specifications, batch
Auxiliary materialsAdhesive + primer + trim pieces + groutSubstrate conditions, termination complexity
ManualMounting area × labor cost per unit areaForm complexity, floor height, proportion of special shapes

◆Estimate: Specific unit prices vary with pattern, thickness, order quantity, and construction conditions; a wide range is normal. This article does not provide a single quotation to avoid misleading; for project pricing, please provide the area, pattern, and delivery location.

VIII. Common questions (FAQ)

Is linen weave flexible stone suitable for a space like a restaurant cashier counter?

Suitable. The woven texture has a handmade feel up close and reads as a whole soft base color from a distance. This project uses it for the barbecue restaurant's cashier counter backdrop, self-service counter and lobby walls. The warm brown linen-woven flexible stone presents a rich, full base color under the warm light of the grill.

Can curved walls and column cladding be done in one continuous piece?

Yes. The material has a certain flexibility and can be bent within a certain radius, so columns, curved walls and irregular corners can achieve full-panel wrapping with continuous seams. The specific usable radius depends on the selected model, thickness and substrate conditions; it is recommended to first test-bend a physical sample at the corresponding curvature to confirm.

How long does the schedule generally take?

This project is approximately 780 ㎡, staffed with 4 people, and completed in 14 working days (including substrate preparation and finishing). The installation itself accounts for about 11 working days, with the remainder for substrate work, layout marking, and acceptance inspection. The main variable in the schedule is substrate condition—substrate rework will directly eat into the time saved on installation.

Can it be used in damp areas?

Yes. The material itself does not absorb water, and after construction the wall surface is not prone to dampness or mildew, so it can be used in humid environments and underground spaces. For wet areas such as bathrooms, it is recommended to confirm the specific scope in conjunction with the wet/dry zoning plan.

What about fire performance?

The material has flame-retardant properties; the specific combustion performance ratingshall be in accordance with the valid inspection report of the selected model. If the project has specific requirements for fire rating, please specify before placing an order.

How much difference in texture is there compared to natural stone?

Differences are visible up close: natural stone has naturally occurring random variation, while the texture of Linen Weave Soft Stone flexible stone is formed by embossing or printing, giving greater consistency within the same product. From a distance the overall look is similar. When placing natural stone and flexible materials on adjacent walls in the same space, it is advisable to make a small sample comparison first.

Can old walls be renovated by direct pasting?

If the original wall surface is firm and has no hollowing, it is possible; old tile surfaces can also be covered directly. But before construction, each surface must be checked for hollowing, and hollowed areas must be knocked out and redone—this step cannot be skipped.

Does the material have test reports? What standard does it follow?

Execution JG/T 540-2017 'Building Flexible Stone-faced Decorative Material' (issued by the Ministry of Housing and Urban-Rural Development). Environmental protection and combustion performance test reports for the corresponding models can be provided with the goods.

How to confirm color and texture?

It is advisable to request physical samples and compare them under the project's actual lighting before deciding the color number. There are differences between screen display and actual materials; in particular, stone-texture materials look different at different angles and color temperatures.

Can a single damaged panel be replaced later?

Yes. During layout, the seam lines and termination positions have already been determined, and a single piece can be pried out from the termination for replacement. It is recommended to reserve 1–2 boxes of same-batch material as spares at delivery.

IX. Project File and Contact Information

Project Content
LocationDuyun City, Guizhou Province
Main material.Linen weave flexible stone (warm brown)
Material seriesCloth Texture and Weave Series
Construction areaApprox. 780 ㎡
Schedule14 working days
Related sectionsProject Cases · Dining cashier counter
Implementation standardsJG/T 540-2017

Similar projects can be found at Project Cases View column; for material specifications and colors see Cloth Texture and Weave Series.


Legend and specification notes

  • ★Project experience = Industry common practice and experience range, not a reference for national standard data.
  • ◆Estimate = Estimated value calculated based on the scale,not an actual measured bill; actual conditions are subject to the contract agreement and site conditions.
  • Material parameters are taken from the corresponding product file; combustion performance, environmental grade, etc. are subject to the valid test report for the selected model.
  • Area, schedule, and quantity are estimates based on industry-scale figures; the calculation process is provided and can be reviewed against your own project's basis.

Find the appropriate wall expression for your project.

Provide the type of space, wall area, and design intention. Communicate about materials, samples, and quotations.

Consulting project material selection ↗
Contact phone number Product Catalog Free Sample
WeChat ID copied